Salesforce Certified Field Service Consultant (FS-Con-101) Exam - Topic 4 Question 2 Discussion

Actual exam question for Salesforce's Salesforce Certified Field Service Consultant (FS-Con-101) exam
Question #: 2
Topic #: 4
[All Salesforce Certified Field Service Consultant (FS-Con-101) Questions]

Universal Containers wants to schedule deliveries using Salesforce Field Service. Each delivery requires that an installation and safety inspection be performed by different Technicians during the same day. The safety inspection needs to be executed after the installation is complete.

How should the Consultant use Complex Work to meet this requirement?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

0/2000 characters
Janna
4 months ago
C is too simple for this scenario, I don’t think it’ll work.
upvoted 0 times
...
Mireya
4 months ago
I’m leaning towards A, but B seems solid too.
upvoted 0 times
...
Tandra
4 months ago
Wait, can you really do it all in one day? Sounds tricky.
upvoted 0 times
...
Francis
4 months ago
Definitely agree with B! It covers both requirements.
upvoted 0 times
...
Filiberto
4 months ago
I think option B makes the most sense here.
upvoted 0 times
...
Claribel
5 months ago
I feel like "Start After Finish" is definitely the right approach, but I’m not sure if we need to add any other dependencies to ensure the timing works out.
upvoted 0 times
...
Joaquin
5 months ago
I practiced a similar question where we had to schedule multiple tasks. I think "Same Day" dependencies could be relevant since both tasks need to happen on the same day.
upvoted 0 times
...
Tiera
5 months ago
I’m a bit unsure about the "Same Resource" part. Does that mean both tasks have to be done by the same technician? That seems tricky for this scenario.
upvoted 0 times
...
Glenn
5 months ago
I remember we discussed the importance of sequencing tasks, especially when one depends on the completion of another. I think "Start After Finish" might be key here.
upvoted 0 times
...
Lelia
5 months ago
Wait, are logs and views also options? I'm a bit confused now. I better double-check the information in my notes to make sure I don't miss anything.
upvoted 0 times
...
Jerlene
5 months ago
Hmm, I'm a little unsure about this one. I'll need to review the delimited text parsing strategy details to make sure I understand the right approach.
upvoted 0 times
...
Malinda
5 months ago
Hmm, I'm a bit unsure about this one. I'll need to think through the different possibilities and try to eliminate the less likely options.
upvoted 0 times
...
Carisa
5 months ago
I'm a little confused by this question. The options all seem to be related to RRC connection procedures, but I'm not sure which one is specifically triggered by the statistics of successful connections. I'll need to think this through carefully.
upvoted 0 times
...