Northern Trail Outfitters is undergoing a service Cloud implementation and has decided to use the Scrum methodology for the implementation. A business analyst (BA) received an urgent, high-priority change request in the middle of a sprint.Which step should the BA take next?
A) Begin working on the change request as soon as the team has capacity.
B) Add the change request to the prioritized for the next sprint.
C) De-prioritize some user stories and add the change request to the current sprint.