Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PRINCE2 Exam PRINCE2-Practitioner Topic 7 Question 91 Discussion

Actual exam question for PRINCE2's PRINCE2-Practitioner exam
Question #: 91
Topic #: 7
[All PRINCE2-Practitioner Questions]

Which of the following is NOT a trigger for the project manager to authorize a work package?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Brynn
5 days ago
I disagree, I believe it's D) Reporting highlights.
upvoted 0 times
...
Bernardine
7 days ago
This question is a real head-scratcher. I hope the exam has more multiple-choice options than just these four!
upvoted 0 times
...
Tequila
7 days ago
I think the answer is B) Corrective Action.
upvoted 0 times
...
Reyes
9 days ago
I'm pretty sure the answer is C. An exception plan that's been approved should be a valid trigger.
upvoted 0 times
...
My
15 days ago
B is the correct answer. Corrective action is not a trigger for authorizing a work package.
upvoted 0 times
...
Argelia
16 days ago
I think the answer is D. Reporting highlights doesn't seem like a valid trigger for authorizing a work package.
upvoted 0 times
Aretha
3 days ago
A) Stage Authorization
upvoted 0 times
...
...

Save Cancel