Which of the following is NOT a trigger for the project manager to authorize a work package?
Suggested Answer: D
Get Premium PRINCE2 Practitioner Questions
as Interactive Web-Based Practice Test or PDF
Real Exam Format
Detailed Explanations
Instant Access
Get Your Practice Test
25 comments · newest first
AL
Alex
11 months ago
Reporting highlights? Really? That seems off.
BO
Boris
11 months ago
Exception plan approved? That's a solid trigger too.
HE
Herman
11 months ago
Wait, are we sure about that? Sounds surprising!
AN
Anglea
11 months ago
I think Corrective Action is also a trigger.
NA
Na
12 months ago
Stage Authorization is definitely a trigger.
EV
Evette
12 months ago
I vaguely recall that reporting highlights might not be a trigger, but I need to double-check my notes on that.
HE
Herman
1 year ago
Exception plans seem like they would require authorization, but I'm a bit confused about reporting highlights.
AL
Alayna
1 year ago
I practiced a similar question where corrective action was mentioned as a trigger, so I feel like that's not the answer here.
LO
Lottie
1 year ago
I think I remember that stage authorization is definitely a trigger, but I'm not sure about reporting highlights.
CE
Celestina
1 year ago
Okay, let me walk through this step-by-step. Corrective Action and Exception plan approved both seem like valid triggers, so I'll eliminate those. That leaves Stage Authorization and Reporting highlights. I think Reporting highlights is the one that's not a trigger.
ME
Mendy
1 year ago
Reporting highlights? That doesn't seem like it would be a trigger for authorizing a work package. I'm going to go with that as my answer.
MA
Mable
1 year ago
Hmm, I'm a little confused on this one. I'll need to think it through carefully to figure out which of these is not a trigger.
JU
Juliana
1 year ago
I'm pretty sure Stage Authorization is a trigger for the project manager to authorize a work package, so that can't be the answer.
CH
Chanel
1 year ago
I think it's C) Exception plan approved because that's when a deviation from the plan is identified.
TE
Tequila
1 year ago
But corrective action is usually taken after a work package is authorized, right?
LE
Leontine
1 year ago
Wait, is the project manager supposed to authorize work packages or just go on coffee breaks? I'm joking, but this question is tricky!
AD
Adelina
1 year ago
A) Stage Authorization
BR
Brynn
1 year ago
I disagree, I believe it's D) Reporting highlights.
BE
Bernardine
1 year ago
This question is a real head-scratcher. I hope the exam has more multiple-choice options than just these four!
TE
Tequila
1 year ago
I think the answer is B) Corrective Action.
RE
Reyes
1 year ago
I'm pretty sure the answer is C. An exception plan that's been approved should be a valid trigger.
MY
My
1 year ago
B is the correct answer. Corrective action is not a trigger for authorizing a work package.
AR
Argelia
1 year ago
I think the answer is D. Reporting highlights doesn't seem like a valid trigger for authorizing a work package.
IL
Iluminada
1 year ago
B) Corrective Action
AR
Aretha
1 year ago
A) Stage Authorization