Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PRINCE2 Practitioner Exam - Topic 7 Question 91 Discussion

Actual exam question for PRINCE2's PRINCE2 Practitioner exam
Question #: 91
Topic #: 7
[All PRINCE2 Practitioner Questions]

Which of the following is NOT a trigger for the project manager to authorize a work package?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

0/2000 characters
Alex
4 months ago
Reporting highlights? Really? That seems off.
upvoted 0 times
...
Boris
4 months ago
Exception plan approved? That's a solid trigger too.
upvoted 0 times
...
Herman
5 months ago
Wait, are we sure about that? Sounds surprising!
upvoted 0 times
...
Anglea
5 months ago
I think Corrective Action is also a trigger.
upvoted 0 times
...
Na
5 months ago
Stage Authorization is definitely a trigger.
upvoted 0 times
...
Evette
5 months ago
I vaguely recall that reporting highlights might not be a trigger, but I need to double-check my notes on that.
upvoted 0 times
...
Herman
6 months ago
Exception plans seem like they would require authorization, but I'm a bit confused about reporting highlights.
upvoted 0 times
...
Alayna
6 months ago
I practiced a similar question where corrective action was mentioned as a trigger, so I feel like that's not the answer here.
upvoted 0 times
...
Lottie
6 months ago
I think I remember that stage authorization is definitely a trigger, but I'm not sure about reporting highlights.
upvoted 0 times
...
Celestina
6 months ago
Okay, let me walk through this step-by-step. Corrective Action and Exception plan approved both seem like valid triggers, so I'll eliminate those. That leaves Stage Authorization and Reporting highlights. I think Reporting highlights is the one that's not a trigger.
upvoted 0 times
...
Mendy
6 months ago
Reporting highlights? That doesn't seem like it would be a trigger for authorizing a work package. I'm going to go with that as my answer.
upvoted 0 times
...
Mable
7 months ago
Hmm, I'm a little confused on this one. I'll need to think it through carefully to figure out which of these is not a trigger.
upvoted 0 times
...
Juliana
7 months ago
I'm pretty sure Stage Authorization is a trigger for the project manager to authorize a work package, so that can't be the answer.
upvoted 0 times
...
Chanel
7 months ago
I think it's C) Exception plan approved because that's when a deviation from the plan is identified.
upvoted 0 times
...
Tequila
7 months ago
But corrective action is usually taken after a work package is authorized, right?
upvoted 0 times
...
Leontine
8 months ago
Wait, is the project manager supposed to authorize work packages or just go on coffee breaks? I'm joking, but this question is tricky!
upvoted 0 times
Adelina
7 months ago
A) Stage Authorization
upvoted 0 times
...
...
Brynn
9 months ago
I disagree, I believe it's D) Reporting highlights.
upvoted 0 times
...
Bernardine
9 months ago
This question is a real head-scratcher. I hope the exam has more multiple-choice options than just these four!
upvoted 0 times
...
Tequila
9 months ago
I think the answer is B) Corrective Action.
upvoted 0 times
...
Reyes
9 months ago
I'm pretty sure the answer is C. An exception plan that's been approved should be a valid trigger.
upvoted 0 times
...
My
9 months ago
B is the correct answer. Corrective action is not a trigger for authorizing a work package.
upvoted 0 times
...
Argelia
9 months ago
I think the answer is D. Reporting highlights doesn't seem like a valid trigger for authorizing a work package.
upvoted 0 times
Iluminada
7 months ago
B) Corrective Action
upvoted 0 times
...
Aretha
8 months ago
A) Stage Authorization
upvoted 0 times
...
...

Save Cancel