PRINCE2 Practitioner Exam - Topic 4 Question 89 Discussion
Scenario:The Ministry of Food Hygiene (MFH) has a quality management system which contains a document control process to manage all documentation requirements. The document control process was created by the MFH Quality Manager, who now maintains all of MFH's documents and performs an organization-wide configuration management role. The MFH Quality Manager will administer the configuration management procedure for the Restructuring project since this must comply with the MFH document control process.According to PRINCE2, which statement about appointing the MFH Quality Manager to administer the configuration management procedure is correct?
C) The MFH Quality Manager would be suitable to perform this task because he is the author of the document control process and is likely to have the knowledge required for this role.
A) The MFH Quality Manager should administer the configuration management procedure on this project because this task should always be assigned to corporate or programme management.
B) The MFH Quality Manager should only administer the configuration management procedure on one project at a time. If the MFH Quality Manager already performs this task on another project, another individual should be appointed.
Raul
6 months agoTracey
6 months agoCarman
6 months agoRosita
6 months agoAlberta
6 months agoJamal
7 months agoNarcisa
7 months agoMeghann
7 months agoMaryann
7 months agoColton
8 months agoJordan
8 months agoJolene
8 months agoTeri
8 months agoDominque
8 months agoVirgie
10 months agoAlisha
9 months agoJuliann
10 months agoPansy
9 months agoIsadora
9 months agoDorothy
10 months agoVictor
10 months agoDominque
10 months agoJettie
11 months agoEdison
11 months agoOlene
10 months agoAlita
10 months agoTegan
10 months agoEttie
11 months agoDorothy
11 months ago