PRINCE2 Practitioner Exam - Topic 4 Question 89 Discussion
Scenario:The Ministry of Food Hygiene (MFH) has a quality management system which contains a document control process to manage all documentation requirements. The document control process was created by the MFH Quality Manager, who now maintains all of MFH's documents and performs an organization-wide configuration management role. The MFH Quality Manager will administer the configuration management procedure for the Restructuring project since this must comply with the MFH document control process.According to PRINCE2, which statement about appointing the MFH Quality Manager to administer the configuration management procedure is correct?
C) The MFH Quality Manager would be suitable to perform this task because he is the author of the document control process and is likely to have the knowledge required for this role.
A) The MFH Quality Manager should administer the configuration management procedure on this project because this task should always be assigned to corporate or programme management.
B) The MFH Quality Manager should only administer the configuration management procedure on one project at a time. If the MFH Quality Manager already performs this task on another project, another individual should be appointed.
Raul
9 months agoTracey
9 months agoCarman
9 months agoRosita
9 months agoAlberta
9 months agoJamal
10 months agoNarcisa
10 months agoMeghann
10 months agoMaryann
10 months agoColton
11 months agoJordan
11 months agoJolene
11 months agoTeri
11 months agoDominque
11 months agoVirgie
1 year agoAlisha
12 months agoJuliann
1 year agoPansy
12 months agoIsadora
12 months agoDorothy
1 year agoVictor
1 year agoDominque
1 year agoJettie
1 year agoEdison
1 year agoOlene
1 year agoAlita
1 year agoTegan
1 year agoEttie
1 year agoDorothy
1 year ago