PRINCE2 Practitioner Exam - Topic 4 Question 6 Discussion

Actual exam question for PRINCE2's PRINCE2 Practitioner exam
Question #: 6
Topic #: 4
[All PRINCE2 Practitioner Questions]

The 'capability to provide health and safety training' has been delivered. During the 'closing a project' process, the marketing department sent an e-mail to all key customers reminding them of the deadline to comply with the new government legislation, with an aim to build relationships with their customers.

Which theme is being applied?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

0/2000 characters
Markus
4 months ago
Not sure if this is really about change...
upvoted 0 times
...
Na
4 months ago
Wait, are they really sending emails to all customers?
upvoted 0 times
...
Hubert
5 months ago
Definitely a risk management theme here.
upvoted 0 times
...
Royal
5 months ago
I think it's more about organization.
upvoted 0 times
...
Marguerita
5 months ago
Sounds like a clear focus on compliance!
upvoted 0 times
...
Kimi
5 months ago
I feel like 'Plans' could be relevant here too, as the marketing department is planning to engage with customers about the deadline.
upvoted 0 times
...
Alica
5 months ago
I'm leaning towards 'Change' because the email is about adapting to new government legislation, but I could be mixing it up with another theme.
upvoted 0 times
...
Kanisha
5 months ago
I think this might relate to the 'Risk' theme since it involves compliance with legislation, but I'm not entirely sure.
upvoted 0 times
...
Adelina
5 months ago
I remember a practice question about communication in projects, and it seems like this could fit under 'Organization' because it's about managing relationships.
upvoted 0 times
...
Brice
5 months ago
I'm a bit unsure about the specifics of how liability is transferred in the other acquisition types listed. I'll need to review those details to be confident in my answer.
upvoted 0 times
...
Victor
5 months ago
Hmm, this seems like a tricky one. I'll need to think carefully about the relationship between event types and event classes in Subledger Accounting.
upvoted 0 times
...
Susana
6 months ago
This looks like a straightforward question about the ntpdate command. I'm pretty confident I know the answer, but I'll double-check the details just to be sure.
upvoted 0 times
...

Save Cancel