PRINCE2 Practitioner Exam - Topic 4 Question 32 Discussion
During stage 3, the team manager reports that the work to update the 'corporate quality procedures' has been completed and the product is ready to be delivered.What should project assurance do next?
C) Verify that all the products to be delivered by the work package are approved.
A) Update the team plan to show that the work package is complete.
B) Check the work package and follow the procedure to deliver completed products.
D) Update the stage plan to show the work package as completed.
Yolando
10 months agoViki
10 months agoRuby
11 months agoJeannetta
11 months agoJani
11 months agoCrista
11 months agoBobbye
11 months agoChristiane
11 months agoKristeen
11 months agoLatricia
11 months agoLeah
11 months agoDelfina
11 months agoDarnell
11 months agoDelbert
11 months agoChau
11 months agoJessenia
11 months agoRusty
11 months agoLaurel
12 months agoGerald
12 months ago