PRINCE2 Practitioner Exam - Topic 4 Question 32 Discussion

Actual exam question for PRINCE2's PRINCE2 Practitioner exam
Question #: 32
Topic #: 4
[All PRINCE2 Practitioner Questions]

During stage 3, the team manager reports that the work to update the 'corporate quality procedures' has been completed and the product is ready to be delivered.

What should project assurance do next?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

0/2000 characters
Yolando
4 months ago
Totally agree with B, let's stick to the process!
upvoted 0 times
...
Viki
4 months ago
Wait, are we sure the quality procedures were really updated?
upvoted 0 times
...
Ruby
5 months ago
A seems too early, we need to check everything first.
upvoted 0 times
...
Jeannetta
5 months ago
I think C is crucial too, can't deliver without approvals.
upvoted 0 times
...
Jani
5 months ago
B is the right move, gotta follow the delivery procedure!
upvoted 0 times
...
Crista
5 months ago
I'm leaning towards option C, verifying approvals, but I also remember something about checking the work package itself. It's a bit confusing!
upvoted 0 times
...
Bobbye
5 months ago
I feel like updating the team plan is important, but I can't recall if that's what project assurance does. It seems like it could be part of the process.
upvoted 0 times
...
Christiane
5 months ago
I remember a similar question where we had to verify approvals before delivery. So, maybe verifying that all products are approved is the right step?
upvoted 0 times
...
Kristeen
5 months ago
I think project assurance should probably check the work package and follow the procedure to deliver completed products. That sounds right, but I'm not entirely sure.
upvoted 0 times
...
Latricia
5 months ago
I’m leaning towards option C, but I wonder if we should also check the procedures for delivery as mentioned in other questions we practiced.
upvoted 0 times
...
Leah
5 months ago
I feel like updating the team plan is important, but it seems like there’s more to do before that.
upvoted 0 times
...
Delfina
5 months ago
I remember a practice question where we had to check the work package, so maybe option B is the right choice here?
upvoted 0 times
...
Darnell
5 months ago
I think project assurance should verify that all products are approved before delivery, but I'm not completely sure if that's the first step.
upvoted 0 times
...
Delbert
5 months ago
Hmm, I'm a bit confused about the difference between put and post. I'll have to think this through carefully.
upvoted 0 times
...
Chau
5 months ago
Hmm, I'm not totally sure about this one. I know the critical path method is a common schedule analysis technique, but I can't remember if it accounts for resource limitations. I'll have to think this through carefully.
upvoted 0 times
...
Jessenia
5 months ago
Okay, this looks straightforward. I'll need to find the design elements in the documents and save them as a custom theme called LabTheme.
upvoted 0 times
...
Rusty
5 months ago
I've got this! The first byte indicates a 3-byte UTF-8 character, so the next byte will start with 10.
upvoted 0 times
...
Laurel
6 months ago
I'm leaning towards None of the above because it feels like a trick question, but I could be misremembering the key principles.
upvoted 0 times
...
Gerald
6 months ago
Wait, isn't an underwriter the one who actually determines risk levels? I'm a bit confused about these terms.
upvoted 0 times
...

Save Cancel