PRINCE2 Practitioner Exam - Topic 4 Question 32 Discussion
During stage 3, the team manager reports that the work to update the 'corporate quality procedures' has been completed and the product is ready to be delivered.What should project assurance do next?
C) Verify that all the products to be delivered by the work package are approved.
A) Update the team plan to show that the work package is complete.
B) Check the work package and follow the procedure to deliver completed products.
D) Update the stage plan to show the work package as completed.
Yolando
7 months agoViki
7 months agoRuby
8 months agoJeannetta
8 months agoJani
8 months agoCrista
8 months agoBobbye
8 months agoChristiane
8 months agoKristeen
8 months agoLatricia
8 months agoLeah
8 months agoDelfina
8 months agoDarnell
8 months agoDelbert
8 months agoChau
8 months agoJessenia
8 months agoRusty
8 months agoLaurel
9 months agoGerald
9 months ago