PRINCE2 Practitioner Exam - Topic 4 Question 32 Discussion
During stage 3, the team manager reports that the work to update the 'corporate quality procedures' has been completed and the product is ready to be delivered.What should project assurance do next?
C) Verify that all the products to be delivered by the work package are approved.
A) Update the team plan to show that the work package is complete.
B) Check the work package and follow the procedure to deliver completed products.
D) Update the stage plan to show the work package as completed.
Yolando
9 months agoViki
9 months agoRuby
9 months agoJeannetta
9 months agoJani
9 months agoCrista
10 months agoBobbye
10 months agoChristiane
10 months agoKristeen
10 months agoLatricia
10 months agoLeah
10 months agoDelfina
10 months agoDarnell
10 months agoDelbert
10 months agoChau
10 months agoJessenia
10 months agoRusty
10 months agoLaurel
10 months agoGerald
10 months ago