PRINCE2 Practitioner Exam - Topic 4 Question 31 Discussion
The project board has asked user and supplier assurance to review all product descriptions relating to the 'updated corporate quality procedures', prior to authorizing the stage plan for stage 3.Is this appropriate as part of the 'directing a project' process, and why?
D) No, because the project board should review new product descriptions before they authorize the stage 3 plan.
A) Yes, because project assurance should assess whether all stakeholders have been identified, if requested by the project board.
B) Yes, because project assurance should review the stage 3 plan for viability, if requested by the project board.
C) No, because the project manager is responsible for writing product descriptions when creating the stage 3 plan.
Kenneth
10 months agoWilliam
10 months agoLashaunda
11 months agoCherry
11 months agoOliva
11 months agoGlory
11 months agoDong
11 months agoBambi
11 months agoAlecia
11 months agoCrissy
11 months agoSocorro
11 months agoMelynda
12 months agoTasia
12 months ago