PRINCE2 Practitioner Exam - Topic 4 Question 29 Discussion
The project is in stage 3. Zero time tolerance has been given for this stage. When checking progress, the project manager noticed that the checkpoint report from the external supplier of the 'e-learning course' is late. As work package progress information is missing, the project manager has decided to raise an exception report.Is this an appropriate action, and why?
A) Yes, because an exception report should be used to request guidance on how this situation should be handled.
B) Yes, because there is zero time tolerance for this stage the checkpoint report must be delivered on time.
C) No, because the project manager should check the operations and maintenance interfaces in the work package first.
D) No, because the team plan should be discussed with the supplier to check whether work will be completed on time.
Ariel
10 months agoEric
10 months agoTiffiny
11 months agoVictor
11 months agoRhea
11 months agoGolda
11 months agoTamesha
11 months agoLou
11 months agoDong
11 months agoDonte
11 months agoHerminia
12 months ago