Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PRINCE2 Exam PRINCE2-Practitioner Topic 3 Question 65 Discussion

Actual exam question for PRINCE2's PRINCE2-Practitioner exam
Question #: 65
Topic #: 3
[All PRINCE2-Practitioner Questions]

Scenario

Additional Information

Extract from the Communication Management Strategy.

The project information in the table below is true, but it may not be recorded under the correct heading or be in the correct document.

Using the Project Scenario, select the appropriate response to each of the following 5 questions which have been raised by the Project Board.

The project is now at the end of the initiation stage. Having decided that the Calendar project is a relatively simple project, the Project Manager combined the Starting Up a Project process and the Initiating a Project process. No Project Brief has been produced. Instead the Project Manager used the project mandate to produce a simple Project Initiation Documentation (PlO). The PlO includes the Business Case, a product checklist and several Product Descriptions, Including the Project Product Description. Short sections are also included for each of the strategies and the controls to be applied. The Project Manager has elected to use the Daily Log to record all risks, issues, lessons and quality - results.

After the initiation stage there will be two further stages during which a small number of Work Packages will be authorized. While these are being managed, the Project Manager will hold regular checkpoints, which will support the production of weekly Highlight Reports to the Project Board.

Without a Risk Register how can project risks, the progress of risk actions taken to date and the current status of residual risks be measured?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Jamal
1 months ago
Daily Log, schmaily log. I'd just write 'everything's on fire' in it and call it a day. But I guess the Project Board might not appreciate that level of honesty.
upvoted 0 times
Kris
13 days ago
C) In a simple project, the Project Initiation Documentation (PID) should contain a register for recording risk information and monitoring project risks throughout the delivery stages. The register will now be added to the PID.
upvoted 0 times
...
Haley
16 days ago
Daily Log, schmaily log. I'd just write 'everything's on fire' in it and call it a day. But I guess the Project Board might not appreciate that level of honesty.
upvoted 0 times
...
Beatriz
19 days ago
A) The Daily Log was correctly used to monitor risks during the Starting up a Project process. It will be used to capture all risks, actions, decisions, assumptions
upvoted 0 times
...
...
Joni
1 months ago
Why am I not surprised the Project Manager is cutting corners? Seems like a recipe for disaster. At least they're owned up to it and are going to fix it.
upvoted 0 times
I hope adding the risk register to the PID will help keep things on track.
upvoted 0 times
...
King
1 days ago
C
upvoted 0 times
...
Luisa
2 days ago
B
upvoted 0 times
...
Terrilyn
20 days ago
A
upvoted 0 times
...
...
Barrie
1 months ago
A Risk Register in the PID is definitely the way to go. Gotta have a proper system for monitoring and managing project risks, even on a simple project.
upvoted 0 times
...
Blossom
1 months ago
No Project Brief? That's a bit sloppy. I guess the Project Manager was trying to keep things simple, but skipping key documents is a risky move.
upvoted 0 times
...
Sue
2 months ago
I believe option C makes sense. Adding a register to the PID would help track risks.
upvoted 0 times
...
Allene
2 months ago
I agree, it's important to have a proper way to monitor project risks.
upvoted 0 times
...
Davida
2 months ago
The Daily Log seems like a convenient way to track risks, but it's not really designed for that. Separate registers would be better for proper risk management.
upvoted 0 times
Jesusita
24 days ago
C) In a simple project, the Project Initiation Documentation (PID) should contain a register for recording risk information and monitoring project risks throughout the delivery stages. The register will now be added to the PID.
upvoted 0 times
...
Carin
25 days ago
B) It was not appropriate to use the Daily Log to capture all risks and issues during the Starting up a Project process. Separate registers should have been set up for risks, issues and lessons learned. This will now be done.
upvoted 0 times
...
Marg
1 months ago
A) The Daily Log was correctly used to monitor risks during the Starting up a Project process. It will be used to capture all risks, actions, decisions, assumptions
upvoted 0 times
...
...
Jospeh
2 months ago
I think the question about the Risk Register is tricky.
upvoted 0 times
...

Save Cancel