Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PRINCE2 Exam PRINCE2-Practitioner Topic 2 Question 73 Discussion

Actual exam question for PRINCE2's PRINCE2-Practitioner exam
Question #: 73
Topic #: 2
[All PRINCE2-Practitioner Questions]

Which statement is an appropriate entry for the Lessons Log?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Georgiann
7 days ago
I think C is the appropriate entry for the Lessons Log. It provides a specific detail about the project timeline that would be useful to document.
upvoted 0 times
...
Gerald
9 days ago
Why do you think option D is the right choice?
upvoted 0 times
...
Benedict
10 days ago
I disagree, I believe option D is the correct entry.
upvoted 0 times
...
Gerald
11 days ago
I think the appropriate entry for the Lessons Log is option B.
upvoted 0 times
...

Save Cancel