New Year Sale 2026! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PRINCE2 Practitioner Exam - Topic 2 Question 56 Discussion

Actual exam question for PRINCE2's PRINCE2 Practitioner exam
Question #: 56
Topic #: 2
[All PRINCE2 Practitioner Questions]

Project Scenario

Calendar Project (Note: The companies and people within the scenario are fictional.)

There has been a reduction in fie number of orders at the MNO Manufacturing Company due in part to the increased marketing activities of its competitors. To help counter this, the company has decided to create a promotional calendar for next year for all its current and prospective customers. The end product of this project will be a prepared calendar pack, ready for printing. The design of the calendar will be similar to one sent out previously, and must reflect the company image as described in the existing corporate branding standards. Another project is currently producing a new company logo when is to be printed on each page of the promotional calendar. The prepared calendar pack will consist of:

Design for each month - correctly showing at public holidays and new company logo

Selected photographs- 12 professionally-produced photographs, showing different members of staff

Selected paper and selected envelope - for printing and mailing the calendar

Chosen label design - a competition to design a label will be held as part of this project

List of customers - names and addresses of customers to whom the calendar will be sent.

The project is currently in initiation and will have two further stages:

Stage 2 will include tie activities to:

Create the customer fast using information from the Accounts and Marketing departments

Confirm compliance with the Data Protection Legislation

Create a design for each month - this will be done by the internal creative team

Select and appoint a professional photographer

Gather photograph design ideas from previous project and agree photographic session schedule

Prepare a production cost forecast

Select paper and envelope.

Stage 3 will include the activities to:

Produce and select tie professionally-taken photographs

Hold the label design competition and choose the label design

Assemble the prepared calendar pack.

A production cost forecast, based on the options and costs for the paper, envelope, printing and marketing of the calendar is to be produced in stage 2. However, the actual production and distribution of the calendars is not within the scope of the project. The product cost forecast will be reviewed by the Project Board to determine whether tie project should continue.

It is now 05 October and the prepared calendar pack must be delivered to the print company by 30 November, to enable printing and distribution of the calendar in time for Christmas. The cost of the activities to develop the specialist products and the cost of the project management activities are estimated to be 20,000. There is a project time tolerance of +1 week /-2 weeks and a project cost tolerance of +6,000 / -6,000. A change budget of 500 has been allocated but there is no risk budget.

Whilst identifying the mailing costs for the calendars the Project Manager was surprised to find the costs could vary considerably depending on the size of the package and the delivery service used. For the purpose of this project, the Project Manager has selected an appropriate service but feels that a corporate standard for postage would have reduced the time and effort invested. It could reduce the company's overheads by up to 20k per year. How should the Project Manager record this observation within the project?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

0/2000 characters
Chauncey
4 months ago
A project mandate (A) could really highlight those potential savings effectively!
upvoted 0 times
...
Dallas
4 months ago
I disagree, an Exception Report (C) would be more appropriate for such a significant observation.
upvoted 0 times
...
Oneida
4 months ago
Surprised they didn't have a standard for postage already! Seems like a missed opportunity.
upvoted 0 times
...
Willetta
4 months ago
I think option B makes the most sense. Daily logs are key for tracking.
upvoted 0 times
...
Elvis
4 months ago
Sounds like a solid plan, but they should definitely consider the mailing costs more seriously.
upvoted 0 times
...
Sherita
5 months ago
I thought option A might be right because it outlines potential savings, but I wonder if it’s too formal for just an observation.
upvoted 0 times
...
Kanisha
5 months ago
I’m leaning towards option C since it seems important to inform the Project Board about potential savings, but I’m not confident about the reporting structure.
upvoted 0 times
...
Marylin
5 months ago
I remember a similar question where we had to decide how to document a risk. I feel like option D could be useful too, especially for future projects.
upvoted 0 times
...
Lashandra
5 months ago
I think option B makes sense because it allows the observation to be documented and reviewed later, but I'm not entirely sure if that's the best approach.
upvoted 0 times
...
Leonida
5 months ago
This question seems pretty straightforward to me. The project manager should definitely make an entry in the Lessons Log to document the potential savings from a corporate postage standard. That way, the information can be used to improve future projects, without causing any issues for the current Calendar Project. Easy peasy!
upvoted 0 times
...
Maryrose
5 months ago
Okay, I think I've got a handle on this. Based on the information provided, I would probably recommend recording the observation in the Lessons Log. That way it can be considered for future projects, without disrupting the current project timeline or budget. The other options seem a bit overkill for this particular situation.
upvoted 0 times
...
Luisa
5 months ago
Hmm, this is a tricky one. There are a few different ways the project manager could record that observation, but I'm not sure which one would be the best approach. I might need to re-read the scenario a few times to make sure I fully understand the context and the implications of each option.
upvoted 0 times
...
Sheron
5 months ago
This seems like a pretty straightforward project management question. I'd start by carefully reading through the scenario to understand the key details and requirements. Then I'd consider the different options for recording the project manager's observation about potential savings from a corporate postage standard.
upvoted 0 times
...
Carry
5 months ago
I'm a bit confused on this one. I know the FASB and AICPA both issue important accounting standards, but I'm not sure which one is considered the most authoritative. I'll have to review my materials to refresh my memory.
upvoted 0 times
...
Kayleigh
6 months ago
Hmm, I'm a bit unsure about this one. The question is asking how to accomplish something specific, but the answer choices seem to cover a range of different functionality. I'll need to carefully consider each option to determine the best recommendation.
upvoted 0 times
...
Cecily
10 months ago
Option D all the way! That Lessons Log is like a treasure trove of wisdom. Just imagine the Project Manager's face when they open it up and find this gem of an observation. It'll be like a postage-themed Easter egg!
upvoted 0 times
...
Dannie
10 months ago
I'd go with Option A. A project mandate outlining the potential savings would be a more formal way to present the observation and push for a corporate standard on postage. Plus, it would show the Project Manager is really looking out for the company's best interests.
upvoted 0 times
Jamie
9 months ago
Definitely, it shows the Project Manager is proactive in improving processes.
upvoted 0 times
...
Cristal
9 months ago
It's important to document potential savings for the company.
upvoted 0 times
...
Jenelle
9 months ago
I agree, a project mandate would make it official.
upvoted 0 times
...
Bobbie
9 months ago
Option A sounds like the best choice here.
upvoted 0 times
...
...
Kristeen
10 months ago
Hmm, I'm leaning towards Option B. Making a note in the Daily Log and then transferring it to a Benefits Review Plan at the end of the project seems like a good way to ensure the observation is documented and can be used to identify potential future improvements.
upvoted 0 times
Horace
9 months ago
Definitely, documenting it in the Daily Log will help in tracking potential benefits for future projects.
upvoted 0 times
...
Catalina
9 months ago
That sounds like a practical approach to ensure the observation is not overlooked.
upvoted 0 times
...
Cecil
9 months ago
Option B) Make a note of the observation in the Daily Log to be transferred to a Benefits Review Plan at the end of the project.
upvoted 0 times
...
...
Johnna
11 months ago
Option C seems like the best approach. By recording the observation in an Exception Report to the Project Board, the Project Manager can bring this issue to the attention of the key decision-makers who can then evaluate the potential savings and take appropriate action.
upvoted 0 times
Serina
9 months ago
It's important to document such observations for future reference.
upvoted 0 times
...
Ronald
9 months ago
They can then assess the potential savings and make informed decisions.
upvoted 0 times
...
Yoko
10 months ago
I agree, bringing it to the Project Board's attention is crucial.
upvoted 0 times
...
Layla
10 months ago
Option C seems like the best approach.
upvoted 0 times
...
...
My
11 months ago
I think Option D is the best choice here. Recording the observation in the Lessons Log will ensure that it's documented for future reference and consideration by the corporate management team. They can then decide if a standard for postage should be implemented to save costs across the organization.
upvoted 0 times
Judy
9 months ago
Definitely, keeping track of potential cost-saving opportunities is crucial for the project and the company as a whole.
upvoted 0 times
...
Jesusita
9 months ago
It's important to document these observations for future reference and decision-making.
upvoted 0 times
...
Lajuana
9 months ago
Agreed, having it in the Lessons Log ensures it won't be forgotten and can be reviewed later on.
upvoted 0 times
...
Clay
9 months ago
Option D is a good idea. It will help corporate management consider the potential savings from a standard postage system.
upvoted 0 times
...
Glory
10 months ago
I agree. Keeping a record in the Lessons Log is a smart move for potential cost savings.
upvoted 0 times
...
Franchesca
10 months ago
Option D is a good idea. It will help corporate management consider implementing a standard for postage in the future.
upvoted 0 times
...
Myra
10 months ago
I agree, recording the observation in the Lessons Log is a smart move for future reference.
upvoted 0 times
...
Quentin
10 months ago
Option D is a good idea. It will help corporate management consider implementing a standard for postage in the future.
upvoted 0 times
...
...
Stefanie
11 months ago
I think option A is also a good choice. Producing a project mandate could highlight the benefits of a corporate standard.
upvoted 0 times
...
Beckie
11 months ago
I agree with Maira. It's important to inform the Project Board about potential cost savings.
upvoted 0 times
...
Maira
11 months ago
I think the Project Manager should record the observation in an Exception Report.
upvoted 0 times
...

Save Cancel