Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PRINCE2 Exam PRINCE2-Practitioner Topic 2 Question 56 Discussion

Actual exam question for PRINCE2's PRINCE2-Practitioner exam
Question #: 56
Topic #: 2
[All PRINCE2-Practitioner Questions]

Project Scenario

Calendar Project (Note: The companies and people within the scenario are fictional.)

There has been a reduction in fie number of orders at the MNO Manufacturing Company due in part to the increased marketing activities of its competitors. To help counter this, the company has decided to create a promotional calendar for next year for all its current and prospective customers. The end product of this project will be a prepared calendar pack, ready for printing. The design of the calendar will be similar to one sent out previously, and must reflect the company image as described in the existing corporate branding standards. Another project is currently producing a new company logo when is to be printed on each page of the promotional calendar. The prepared calendar pack will consist of:

Design for each month - correctly showing at public holidays and new company logo

Selected photographs- 12 professionally-produced photographs, showing different members of staff

Selected paper and selected envelope - for printing and mailing the calendar

Chosen label design - a competition to design a label will be held as part of this project

List of customers - names and addresses of customers to whom the calendar will be sent.

The project is currently in initiation and will have two further stages:

Stage 2 will include tie activities to:

Create the customer fast using information from the Accounts and Marketing departments

Confirm compliance with the Data Protection Legislation

Create a design for each month - this will be done by the internal creative team

Select and appoint a professional photographer

Gather photograph design ideas from previous project and agree photographic session schedule

Prepare a production cost forecast

Select paper and envelope.

Stage 3 will include the activities to:

Produce and select tie professionally-taken photographs

Hold the label design competition and choose the label design

Assemble the prepared calendar pack.

A production cost forecast, based on the options and costs for the paper, envelope, printing and marketing of the calendar is to be produced in stage 2. However, the actual production and distribution of the calendars is not within the scope of the project. The product cost forecast will be reviewed by the Project Board to determine whether tie project should continue.

It is now 05 October and the prepared calendar pack must be delivered to the print company by 30 November, to enable printing and distribution of the calendar in time for Christmas. The cost of the activities to develop the specialist products and the cost of the project management activities are estimated to be 20,000. There is a project time tolerance of +1 week /-2 weeks and a project cost tolerance of +6,000 / -6,000. A change budget of 500 has been allocated but there is no risk budget.

Whilst identifying the mailing costs for the calendars the Project Manager was surprised to find the costs could vary considerably depending on the size of the package and the delivery service used. For the purpose of this project, the Project Manager has selected an appropriate service but feels that a corporate standard for postage would have reduced the time and effort invested. It could reduce the company's overheads by up to 20k per year. How should the Project Manager record this observation within the project?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Cecily
14 days ago
Option D all the way! That Lessons Log is like a treasure trove of wisdom. Just imagine the Project Manager's face when they open it up and find this gem of an observation. It'll be like a postage-themed Easter egg!
upvoted 0 times
...
Dannie
16 days ago
I'd go with Option A. A project mandate outlining the potential savings would be a more formal way to present the observation and push for a corporate standard on postage. Plus, it would show the Project Manager is really looking out for the company's best interests.
upvoted 0 times
...
Kristeen
26 days ago
Hmm, I'm leaning towards Option B. Making a note in the Daily Log and then transferring it to a Benefits Review Plan at the end of the project seems like a good way to ensure the observation is documented and can be used to identify potential future improvements.
upvoted 0 times
...
Johnna
1 months ago
Option C seems like the best approach. By recording the observation in an Exception Report to the Project Board, the Project Manager can bring this issue to the attention of the key decision-makers who can then evaluate the potential savings and take appropriate action.
upvoted 0 times
Yoko
7 days ago
I agree, bringing it to the Project Board's attention is crucial.
upvoted 0 times
...
Layla
19 days ago
Option C seems like the best approach.
upvoted 0 times
...
...
My
2 months ago
I think Option D is the best choice here. Recording the observation in the Lessons Log will ensure that it's documented for future reference and consideration by the corporate management team. They can then decide if a standard for postage should be implemented to save costs across the organization.
upvoted 0 times
Lajuana
5 hours ago
Agreed, having it in the Lessons Log ensures it won't be forgotten and can be reviewed later on.
upvoted 0 times
...
Clay
2 days ago
Option D is a good idea. It will help corporate management consider the potential savings from a standard postage system.
upvoted 0 times
...
Glory
23 days ago
I agree. Keeping a record in the Lessons Log is a smart move for potential cost savings.
upvoted 0 times
...
Franchesca
28 days ago
Option D is a good idea. It will help corporate management consider implementing a standard for postage in the future.
upvoted 0 times
...
Myra
1 months ago
I agree, recording the observation in the Lessons Log is a smart move for future reference.
upvoted 0 times
...
Quentin
1 months ago
Option D is a good idea. It will help corporate management consider implementing a standard for postage in the future.
upvoted 0 times
...
...
Stefanie
2 months ago
I think option A is also a good choice. Producing a project mandate could highlight the benefits of a corporate standard.
upvoted 0 times
...
Beckie
2 months ago
I agree with Maira. It's important to inform the Project Board about potential cost savings.
upvoted 0 times
...
Maira
2 months ago
I think the Project Manager should record the observation in an Exception Report.
upvoted 0 times
...

Save Cancel