PRINCE2 Practitioner Exam - Topic 2 Question 51 Discussion
The change control approach defines how products should be controlled and protected during the project. The accreditation of the 'classroom-based training materials' was planned to take place during stage 2. At the end of the stage, the configuration item record shows that the 'classroom-based training materials' have been accredited. However, the project manager decides to request an audit of the product as well.Is this appropriate, and why?
B) Yes, because the change control approach should specify how the configuration item records are approved.
A) Yes, because the project should verify that the recorded status reflects the actual status of the products.
C) No, because the project manager should ensure that the change control approach is tailored to the project.
D) No, because the issue management and change control procedures can be treated as separate, but related, procedures.
Timothy
10 months agoShelia
10 months agoEstrella
10 months agoBette
10 months agoHildegarde
10 months agoRegenia
11 months agoLeanora
11 months agoStephaine
11 months agoStanton
11 months agoSlyvia
11 months agoTom
11 months agoLawana
11 months agoDudley
11 months agoDelsie
11 months agoViola
12 months ago