PRINCE2 Practitioner Exam - Topic 2 Question 43 Discussion
The project is now in stage 2. The 'training venue specifications' will not be delivered to schedule and the stage is forecast to exceed its time tolerance. As a result, the project manager has agreed with the team manager that the 'training venue specifications' will be delivered in stage 3 instead of stage 2.Is this an appropriate action, and why?
D) No, because the stage deviation should be referred to the project board for a decision.
A) Yes, because the project manager should recommend corrective actions required.
B) Yes, because moving the work enables stage 2 to be delivered within tolerance.
C) No, because the team manager should inform the project manager by raising an issue.
Emmett
10 months agoDortha
10 months agoLatanya
11 months agoDaron
11 months agoTresa
11 months agoJina
11 months agoBrandon
11 months agoBong
11 months agoCammy
11 months agoArlie
11 months agoAlecia
11 months agoTamie
12 months agoKarl
12 months ago