PRINCE2 Practitioner Exam - Topic 2 Question 40 Discussion

Actual exam question for PRINCE2's PRINCE2 Practitioner exam
Question #: 40
Topic #: 2
[All PRINCE2 Practitioner Questions]

Scenario

Product Summary

A list of customers will be collated. This will use existing information from the Accounts department about current customers, and existing information from the Marketing department about prospective customers.

Using the tariff of mailing costs available from the Post Office, a production cost forecast will be produced to allow the CEO and the Marketing Director to decide whether to continue with the project. If they decide to continue, they will give the approval to launch the internal label design competition. Competition rules will be required to communicate details of the competition to the staff. The chosen label design will then be selected from the competition entries.

The photos for the calendar must be based on existing photo design ideas available from the Marketing department. The selected photos will be chosen from these. Monthly calendar displays will be created to show the required layout of each page.

Product Breakdown Structure (contains errors)

Extract from Stage Plan for stage 3.

(All entries are true statements but may not be shown under the correct heading or in the correct document).

Using the Project Scenario and the Extract from Stage Plan for stage 3 provided as additional intonation for this question in the Scenario Booklet, answer the following 5 questions.

The Stage Plan for stage 3 has been produced.

The Engineering Manager insists that there are to be no interruptions to operations whilst photographs are being taken of the engineering staff performing their everyday duties and operating machinery. Two weeks ago the professional photographer produced the photo session schedule based on the operational staff schedule. The operational staff schedule is produced weekly and maintained by the Engineering Manager.

None of the 500 change budget has been used to date and this is available for the stage.

Which 2 statements apply to the Planning assumptions section?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

0/2000 characters
Val
4 months ago
Entry 10 should definitely be in the Product Description.
upvoted 0 times
...
Gladis
4 months ago
Moving entry 9 sounds right, it's not in our control.
upvoted 0 times
...
Olive
5 months ago
Wait, how can we delete entry 9? That seems risky.
upvoted 0 times
...
Sheridan
5 months ago
Totally agree, that makes sense!
upvoted 0 times
...
Gearldine
5 months ago
Entry 8 can't be confirmed until all designs are in.
upvoted 0 times
...
Sharee
5 months ago
I’m a bit confused about entry 10. I thought we needed to include all details in the Product Description, so maybe option E makes sense?
upvoted 0 times
...
Fausto
5 months ago
I think we had a practice question about external dependencies, and it seems like option D could apply here since the photographer is external.
upvoted 0 times
...
Tyra
5 months ago
I'm not entirely sure, but I feel like entry 9 should have been approved earlier, so maybe option C is right?
upvoted 0 times
...
Arlean
5 months ago
I remember we discussed the importance of confirming assumptions before finalizing the planning section. I think option A might be correct.
upvoted 0 times
...
Janella
5 months ago
The key is to make sure you install the Falcon package before you register the sensor. I'd go with option A to play it safe.
upvoted 0 times
...
Melynda
6 months ago
I'm feeling a bit confused about this one. I know we need to create a query for a bar graph, but I'm not sure which of these functions would be the best to use. I'll have to review my notes and try to figure this out.
upvoted 0 times
...
Coletta
10 months ago
I agree with option C. The photo session schedule should have been approved earlier, so it doesn't belong in the planning assumptions for stage 3.
upvoted 0 times
Reita
9 months ago
Yes, it makes sense to delete entry 9 from the planning assumptions for stage 3.
upvoted 0 times
...
Cassi
9 months ago
I agree, the photo session schedule should have been sorted out in a previous stage.
upvoted 0 times
...
Simona
9 months ago
I think option C is the best choice. The photo session schedule should have been approved earlier.
upvoted 0 times
...
...
Sabra
11 months ago
Haha, I bet the Engineering Manager is really protective of their operations. No interruptions allowed, even for a photo shoot! This is going to be an interesting project to manage.
upvoted 0 times
Mozell
9 months ago
C) Delete entry 9 because the photo session schedule should have been approved as part of stage 2.
upvoted 0 times
...
Marguerita
9 months ago
B) Move entry 8 to External dependencies because the label designs are created outside of the scope of the project.
upvoted 0 times
...
Viva
9 months ago
A) No change to entry 8 because this cannot be confirmed until all of the label designs entries have been received and an assessment made.
upvoted 0 times
...
...
Alyce
11 months ago
Why do you think that?
upvoted 0 times
...
Dick
11 months ago
I'm not sure about deleting entry 9. The photo session schedule should have been approved in stage 2, but it's still relevant to the planning assumptions for stage 3.
upvoted 0 times
Micaela
10 months ago
I agree, it makes sense to consider it as an external dependency since it's not directly controlled by the project team.
upvoted 0 times
...
Louann
10 months ago
I think we should move entry 9 to External dependencies because the photo session schedule is created by the professional photographer.
upvoted 0 times
...
...
Tawna
11 months ago
I disagree, I believe the correct answer is D.
upvoted 0 times
...
Berry
11 months ago
Option B makes the most sense. The label designs are indeed created outside the project, so they should be considered an external dependency.
upvoted 0 times
Cletus
10 months ago
Yes, it's crucial to address any dependencies early on to avoid delays.
upvoted 0 times
...
Selene
10 months ago
External dependencies can impact the project timeline and resources.
upvoted 0 times
...
Tonette
10 months ago
I agree, it's important to identify external dependencies for better project management.
upvoted 0 times
...
Luisa
10 months ago
Option B makes sense. The label designs are external to the project.
upvoted 0 times
...
...
Alyce
11 months ago
I think the answer is A.