PRINCE2 Practitioner Exam - Topic 2 Question 39 Discussion

Actual exam question for PRINCE2's PRINCE2 Practitioner exam
Question #: 39
Topic #: 2
[All PRINCE2 Practitioner Questions]

Scenario

Additional Information

Extract from the Communication Management Strategy.

The project information in the table below is true, but it may not be recorded under the correct heading or be in the correct document.

Using the Project Scenario, select the appropriate response to each of the following 5 questions which have been raised by the Project Board.

The project is now at the end of the initiation stage. Having decided that the Calendar project is a relatively simple project, the Project Manager combined the Starting Up a Project process and the Initiating a Project process. No Project Brief has been produced. Instead the Project Manager used the project mandate to produce a simple Project Initiation Documentation (PlO). The PlO includes the Business Case, a product checklist and several Product Descriptions, Including the Project Product Description. Short sections are also included for each of the strategies and the controls to be applied. The Project Manager has elected to use the Daily Log to record all risks, issues, lessons and quality - results.

After the initiation stage there will be two further stages during which a small number of Work Packages will be authorized. While these are being managed, the Project Manager will hold regular checkpoints, which will support the production of weekly Highlight Reports to the Project Board.

This question provides a number of changes which may or may not be required to the Extract from the Communication Management Strategy provided in the additional information.

Which statement applies to the Timing of communication activities section?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

0/2000 characters
Na
4 months ago
No change needed for entry 9, it’s spot on!
upvoted 0 times
...
Brent
4 months ago
Wait, no Project Brief? That seems off.
upvoted 0 times
...
Michel
5 months ago
Highlight Reports are definitely a Project Board control.
upvoted 0 times
...
Felicidad
5 months ago
I disagree, it should be in the Project controls.
upvoted 0 times
...
Flo
5 months ago
Entry 9 is crucial for performance timing.
upvoted 0 times
...
Franklyn
5 months ago
I think we discussed that Highlight Reports are indeed a control for the Project Board, so maybe entry 10 should be deleted.
upvoted 0 times
...
Nicolette
5 months ago
I feel like entry 9 is important for understanding when performance reports are due, but I can't recall if it should stay or go.
upvoted 0 times
...
Melissa
5 months ago
This question seems similar to one we practiced where we had to decide on the relevance of communication entries in the PID. I think entry 10 might need to be deleted.
upvoted 0 times
...
Novella
5 months ago
I remember that the timing of communication activities is crucial, but I'm not sure if we should delete entry 9 or not.
upvoted 0 times
...
Fabiola
5 months ago
I think a stem and leaf plot would be the best option here to show the individual readings. It's a simple but effective way to display the data.
upvoted 0 times
...
Flo
5 months ago
I'm not too familiar with the Knowledge Management module, so I'm a bit unsure about this one. I'll have to review the documentation to make sure I understand the capabilities before answering.
upvoted 0 times
...
Angella
6 months ago
Okay, I think I've got this. The case rate is the total amount the hospital charges for the entire inpatient stay, not just a single month. So option D seems like the best answer here.
upvoted 0 times
...
Charlene
10 months ago
Option C is the way to go. Gotta keep that Communication Management Strategy tidy, like a freshly-pressed suit. No room for any loose threads!
upvoted 0 times
Whitney
9 months ago
Absolutely, attention to detail in communication strategy is crucial for project success.
upvoted 0 times
...
Ahmed
9 months ago
Agreed, keeping things organized is key to successful project management.
upvoted 0 times
...
Linn
9 months ago
C) Delete entry 10 because Highlight Reports are a Project Board control, the frequency of which should be recorded in the Project controls section of the Project Initiation Documentation.
upvoted 0 times
...
...
Kati
10 months ago
I bet the Project Manager is wishing they had a copy of the PRINCE2 manual right about now. This exam question is like a test within a test!
upvoted 0 times
...
Myong
10 months ago
Definitely option C. Trying to keep the Communication Management Strategy as lean as possible is a wise move. Let's not clutter it with stuff that belongs elsewhere.
upvoted 0 times
...
Laila
10 months ago
C) Yes, that makes sense. Highlight Reports are a Project Board control, so the frequency should be recorded in the Project Initiation Documentation, not the Communication Management Strategy.
upvoted 0 times
Mireya
9 months ago
C) Yes, that makes sense. Highlight Reports are a Project Board control, so the frequency should be recorded in the Project Initiation Documentation, not the Communication Management Strategy.
upvoted 0 times
...
Kenda
9 months ago
A) Delete entry 9 because activities for controlling the project should be planned as part of Project controls in the Project Initiation Documentation.
upvoted 0 times
...
...
Sophia
10 months ago
B) I agree with this. Entry 9 describes the timing of performance reports, which is relevant to the Communication Management Strategy. No need to delete it.
upvoted 0 times
Lorrie
9 months ago
C) Delete entry 10 because Highlight Reports are a Project Board control, the frequency of which should be recorded in the Project controls section of the Project Initiation Documentation.
upvoted 0 times
...
Tamra
9 months ago
B) No change to entry 9 because it describes the timing of performance reports.
upvoted 0 times
...
Edgar
9 months ago
A) Delete entry 9 because activities for controlling the project should be planned as part of Project controls in the Project Initiation Documentation.
upvoted 0 times
...
...
Yolando
10 months ago
A) Hmm, that's an interesting point. I can see the logic behind deleting entry 9, as controlling the project should be part of the Project Initiation Documentation. But I'm not sure if that's the right approach here.
upvoted 0 times
Lucille
9 months ago
C) Delete entry 10 because Highlight Reports are a Project Board control, the frequency of which should be recorded in the Project controls section of the Project Initiation Documentation.
upvoted 0 times
...
Gayla
10 months ago
B) No change to entry 9 because it describes the timing of performance reports.
upvoted 0 times
...
Justine
10 months ago
A) Hmm, that's an interesting point. I can see the logic behind deleting entry 9, as controlling the project should be part of the Project Initiation Documentation. But I'm not sure if that's the right approach here.
upvoted 0 times
...
...
Sherly
11 months ago
I believe the answer might be A, as controlling the project should be planned as part of Project controls.
upvoted 0 times
...
Ronald
11 months ago
I agree, it's important to understand the correct timing for communication in the project.
upvoted 0 times
...
Sherly
11 months ago
I think the question about the Timing of communication activities is tricky.
upvoted 0 times
...