Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PRINCE2 Exam PRINCE2-Practitioner Topic 2 Question 30 Discussion

Actual exam question for PRINCE2's PRINCE2-Practitioner exam
Question #: 30
Topic #: 2
[All PRINCE2-Practitioner Questions]

The senior user is concerned that the trainers' limited availability could delay their accreditation. This was discussed during the 'starting up a project' process, but during the 'initiating a project' process the project manager notices that it has not been recorded.

Which action should the project manager take FIRST?

Show Suggested Answer Hide Answer
Suggested Answer: A

Comments

Currently there are no comments in this discussion, be the first to comment!


Save Cancel