As a result of experiences on previous projects, a change authority has been established for the Health and Safety Training Project. A key client for the training materials has a representative on the project board.Should their interests be represented within the change authority for the project, and why?
D) No, because their project board member will be able to agree any required changes.
A) Yes, because this will give them a better understanding of the training materials.
B) Yes, because a change authority should consider external stakeholder needs.
C) No, because the change authority should be internal to the ABC organization.