Question #: 17
Topic #: 2
[All PRINCE2-Practitioner Questions]

As a result of experiences on previous projects, a change authority has been established for the Health and Safety Training Project. A key client for the training materials has a representative on the project board.

Should their interests be represented within the change authority for the project, and why?

Show Suggested Answer Hide Answer
Suggested Answer: D