Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PRINCE2 Exam PRINCE2-Practitioner Topic 1 Question 76 Discussion

Actual exam question for PRINCE2's PRINCE2-Practitioner exam
Question #: 76
Topic #: 1
[All PRINCE2-Practitioner Questions]

Which of the following principles describes this statement?

"xxx defines tolerances for each project objective to establish limits of delegated authority"

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Rashida
18 days ago
Haha, 'Manage by exception' all the way! Gotta love those pre-defined tolerance levels, saves us all a headache.
upvoted 0 times
...
Genevieve
22 days ago
I think the key here is 'establish limits of delegated authority'. That's got to be 'Manage by exception'.
upvoted 0 times
...
Dorothea
1 months ago
Definitely 'Manage by exception' - can't have the project manager micromanaging every little detail, am I right?
upvoted 0 times
Alisha
3 days ago
B) Focus on products
upvoted 0 times
...
Josephine
8 days ago
A) Manage by stages
upvoted 0 times
...
...
Viva
1 months ago
Hmm, this sounds like 'Manage by exception' to me. Gotta stay within those delegated limits!
upvoted 0 times
Laurel
9 days ago
I think it's 'Manage by exception' too. We need to stick to those tolerances.
upvoted 0 times
...
...
Margret
2 months ago
I'm not sure, but I think A) Manage by stages could also be a possible answer.
upvoted 0 times
...
Hershel
2 months ago
I agree with Anjelica, because managing by exception allows for tolerances to be set.
upvoted 0 times
...
Anjelica
2 months ago
I think the answer is C) Manage by exception.
upvoted 0 times
...

Save Cancel