PRINCE2 Exam PRINCE2-Practitioner Topic 1 Question 70 Discussion

Actual exam question for PRINCE2's PRINCE2-Practitioner exam
Question #: 70
Topic #: 1
[All PRINCE2-Practitioner Questions]

Who is responsible for committing user resources to the project?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Theron
1 days ago
I agree with Lettie, Senior User is responsible for committing user resources.
upvoted 0 times
...
Alida
9 days ago
The Senior User is responsible for committing user resources to the project, so I think the answer is A.
upvoted 0 times
...
Lettie
16 days ago
I think the answer is A) Senior User.
upvoted 0 times
...