The Sales Director would like to add a new company logo to the 'marketing material'. The change to the project scope has been approved by the project board. It is expected to delay product and stage completion date by 3 days and cost 900. The stage 2 cost tolerance of +1,000 has not been used. The change budget of 500 has not been used.
Which option describes how this change should be funded?
Suggested Answer: D
Get Premium PRINCE2 Practitioner Questions
as Interactive Web-Based Practice Test or PDF
Real Exam Format
Detailed Explanations
Instant Access
Get Your Practice Test
15 comments · newest first
AL
Alex
12 months ago
900 for a logo? That seems a bit steep!
GE
Gerri
12 months ago
Using the change budget is a no-brainer here.
VA
Van
1 year ago
Wait, why would we need additional funding?
CA
Carey
1 year ago
I disagree, option B is the way to go.
LE
Letha
1 year ago
Seems like option A makes the most sense.
LA
Lashonda
1 year ago
I’m leaning towards option D, but I’m not completely confident. It seems like we might need to request additional funding, but I can’t recall the exact rules.
CA
Cathrine
1 year ago
I practiced a similar question where we had to decide on funding options, and I feel like we should use both the change budget and part of the cost tolerance.
SU
Sue
1 year ago
I think option B sounds right since the full 900 can come from the stage 2 cost tolerance, but I’m a bit confused about the change budget.
JA
Janine
1 year ago
I remember that we can use the cost tolerance and change budget together, but I'm not sure how much of each to apply here.
LY
Lyla
1 year ago
This seems straightforward to me. The 900 needed for the change should be taken from the stage 2 cost tolerance, as stated in option B. I'm confident that's the right way to handle this.
RO
Rosendo
1 year ago
Based on the information provided, I believe option A is the correct answer. We can use 400 from the stage 2 cost tolerance and the 500 change budget to cover the 900 cost of the change.
SH
Shakira
1 year ago
Hmm, this is a tricky one. I'm not entirely sure which option is the best approach. I'll need to carefully review the details about the cost tolerance and change budget to decide how to fund this change.
HA
Harley
1 year ago
Okay, let's see. The change is expected to cost 900 and delay the project by 3 days. The stage 2 cost tolerance of +1,000 hasn't been used, and the change budget of 500 is also available. I think option B is the right choice here.
KA
Karma
1 year ago
Hmm, I'm a little unsure about this one. The question mentions minimizing development effort, so I'm not sure if creating a separate release view is the best approach. Maybe option A, using the default view, would be simpler?
MA
Matilda
1 year ago
I'm confident I know the answer to this. The key is understanding the different SQL statements that trigger a new transaction.