PRINCE2 Practitioner Exam - Topic 1 Question 47 Discussion

Posted by Marti on Jul 08, 2023 at 12:42 PM

It is now late October and the project is in stage 3. The label design competition has been held and the photos of the staff have been taken. The CEO and Marketing Director still need to choose the winning label design and the 12 photos for the calendar. However, the Executive has learned that two competitors are issuing calendars to MNO's customers by the middle of November. After analyzing the impact of this Issue, one of the options the Project Manager has presented to the Project Board is to close the project prematurely.

There are a number of key facts relating to this project that would need to be recorded if the project Y-e to be closed now.

Which product should show that without the calendar the company is going to experience difficulties recovering its decline in orders, and alternative solutions are required if the company is going to recover its position?

Get Premium PRINCE2 Practitioner Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
49 comments · newest first
NI
Nidia 12 months ago
Exception Report could work too, but it might not capture the full picture.
JA
Jackie 12 months ago
Totally agree with Ollie. The End Project Report is key!
NA
Natalie 1 year ago
Wait, are they really considering closing it early? That seems risky!
BO
Bo 1 year ago
I think the Benefits Review Plan makes more sense here. It highlights the losses.
OL
Ollie 1 year ago
Definitely the End Project Report. It needs to cover the impact of not having the calendar.
TA
Tawna 1 year ago
I practiced a similar question, and I think the Exception Report is more about deviations from the plan. It doesn't seem to fit this scenario as well as the Benefits Review Plan.
JA
Javier 1 year ago
I feel like the Risk Register could also be important, but it seems more about identifying risks rather than showing the impact of not having the calendar.
RA
Ramonita 1 year ago
I'm not entirely sure, but I remember something about the End Project Report summarizing everything. Could that be relevant here?
TE
Tequila 1 year ago
I think the Benefits Review Plan might be the right choice since it focuses on the expected benefits and how the lack of the calendar could impact those.
AN
Antonio 1 year ago
Ah, I see it now. Object-Oriented Analysis and Design is a key influence of service-orientation, so that must be the answer that is not an influence. Nicely worded question!
RO
Rosio 1 year ago
I think we learned about this in our network architecture class. Pretty sure it's VPC+, but I'm not completely confident.
MI
Millie 1 year ago
This seems like a classic performance issue with a VDI environment. I'd start by looking at the disk I/O limits, as that's often the culprit for slow performance, especially at peak times.
AL
Altha 1 year ago
I think enabling unicast routing could be important, but I'm not entirely sure if it's essential for external connectivity.
MA
Maryrose 1 year ago
Hmm, I think a model-based technique like option A could be a good approach here. If we can create an operational profile, we might be able to simulate real-world usage and test the system's reliability.
NA
Nathalie 1 year ago
The CEO and Marketing Director must be feeling the pressure of those pesky competitors. I bet they wish they could just close the project and go on an early vacation!
CH
Chaya 1 year ago
↳ replying to Nathalie
D) Risk Register
LI
Ligia 1 year ago
↳ replying to Nathalie
C) End Project Report
GE
German 1 year ago
↳ replying to Nathalie
B) Exception Report
CA
Camellia 1 year ago
↳ replying to Nathalie
A) Benefits Review Plan
DE
Detra 2 years ago
Haha, the Risk Register? That's like trying to put out a fire with gasoline. We need something that actually addresses the problem, not just lists the risks.
DA
Danica 1 year ago
↳ replying to Detra
Haha, the Risk Register? That's like trying to put out a fire with gasoline. We need something that actually addresses the problem, not just lists the risks.
TR
Trinidad 1 year ago
↳ replying to Detra
C) End Project Report
FL
Flo 1 year ago
↳ replying to Detra
B) Exception Report
LA
Lashon 1 year ago
↳ replying to Detra
A) Benefits Review Plan
LA
Lavonda 1 year ago
↳ replying to Detra
C) End Project Report
BO
Boris 1 year ago
↳ replying to Detra
C) End Project Report
RO
Rosendo 1 year ago
↳ replying to Detra
B) Exception Report
SH
Sharika 1 year ago
↳ replying to Detra
A) Benefits Review Plan
LE
Levi 1 year ago
↳ replying to Detra
B) Exception Report
ST
Stevie 2 years ago
↳ replying to Detra
A) Benefits Review Plan
NO
Noel 2 years ago
The Exception Report could work, but it might not provide the comprehensive overview that the End Project Report would.
MI
Michel 2 years ago
I disagree. I think we should go with option A) Benefits Review Plan to analyze the impact of not having the calendar on our orders.
AD
Adrianna 2 years ago
I agree with Lauryn. The End Project Report will help us document the key facts and reasons for closing the project prematurely.
LA
Lauryn 2 years ago
I think we should choose option C) End Project Report.
GL
Gladis 2 years ago
I'm not sure, but maybe we should also consider option A) Benefits Review Plan to assess the impact of not having the calendar on our orders.
HU
Hui 2 years ago
I agree with Vicki. The End Project Report will help us document the key facts and reasons for closing the project prematurely.
RO
Rodolfo 2 years ago
I'm not sure if the Benefits Review Plan is the right option since the focus seems to be on the challenges faced rather than the benefits achieved.
BO
Bok 1 year ago
↳ replying to Rodolfo
That makes sense. It's important to document everything for future reference.
JA
Janessa 1 year ago
↳ replying to Rodolfo
I agree, it would provide a comprehensive overview of the project's challenges and potential solutions.
ME
Melodie 1 year ago
↳ replying to Rodolfo
C) End Project Report
FL
Fletcher 1 year ago
↳ replying to Rodolfo
I think the End Project Report would be more suitable in this situation.
AL
Alaine 1 year ago
↳ replying to Rodolfo
D) Risk Register
AL
Allene 1 year ago
↳ replying to Rodolfo
C) End Project Report
NA
Nathan 1 year ago
↳ replying to Rodolfo
B) Exception Report
TR
Tracey 2 years ago
↳ replying to Rodolfo
A) Benefits Review Plan
EL
Eloisa 2 years ago
↳ replying to Rodolfo
B) Exception Report
ME
Melda 2 years ago
↳ replying to Rodolfo
A) Benefits Review Plan
VI
Vicki 2 years ago
I think we should choose option C) End Project Report.
VA
Vanesa 2 years ago
The End Project Report seems like the appropriate choice here. It would capture all the key facts and highlight the impact of the competitors issuing calendars early.