Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PRINCE2 Exam PRINCE2-Practitioner Topic 1 Question 47 Discussion

Actual exam question for PRINCE2's PRINCE2-Practitioner exam
Question #: 47
Topic #: 1
[All PRINCE2-Practitioner Questions]

It is now late October and the project is in stage 3. The label design competition has been held and the photos of the staff have been taken. The CEO and Marketing Director still need to choose the winning label design and the 12 photos for the calendar. However, the Executive has learned that two competitors are issuing calendars to MNO's customers by the middle of November. After analyzing the impact of this Issue, one of the options the Project Manager has presented to the Project Board is to close the project prematurely.

There are a number of key facts relating to this project that would need to be recorded if the project Y-e to be closed now.

Which product should show that without the calendar the company is going to experience difficulties recovering its decline in orders, and alternative solutions are required if the company is going to recover its position?

Show Suggested Answer Hide Answer

Contribute your Thoughts:

Nathalie
17 days ago
The CEO and Marketing Director must be feeling the pressure of those pesky competitors. I bet they wish they could just close the project and go on an early vacation!
upvoted 0 times
Camellia
3 days ago
A) Benefits Review Plan
upvoted 0 times
...
...
Detra
1 months ago
Haha, the Risk Register? That's like trying to put out a fire with gasoline. We need something that actually addresses the problem, not just lists the risks.
upvoted 0 times
Levi
8 days ago
B) Exception Report
upvoted 0 times
...
Stevie
29 days ago
A) Benefits Review Plan
upvoted 0 times
...
...
Noel
1 months ago
The Exception Report could work, but it might not provide the comprehensive overview that the End Project Report would.
upvoted 0 times
...
Michel
1 months ago
I disagree. I think we should go with option A) Benefits Review Plan to analyze the impact of not having the calendar on our orders.
upvoted 0 times
...
Adrianna
1 months ago
I agree with Lauryn. The End Project Report will help us document the key facts and reasons for closing the project prematurely.
upvoted 0 times
...
Lauryn
2 months ago
I think we should choose option C) End Project Report.
upvoted 0 times
...
Gladis
2 months ago
I'm not sure, but maybe we should also consider option A) Benefits Review Plan to assess the impact of not having the calendar on our orders.
upvoted 0 times
...
Hui
2 months ago
I agree with Vicki. The End Project Report will help us document the key facts and reasons for closing the project prematurely.
upvoted 0 times
...
Rodolfo
2 months ago
I'm not sure if the Benefits Review Plan is the right option since the focus seems to be on the challenges faced rather than the benefits achieved.
upvoted 0 times
Janessa
14 hours ago
I agree, it would provide a comprehensive overview of the project's challenges and potential solutions.
upvoted 0 times
...
Melodie
2 days ago
C) End Project Report
upvoted 0 times
...
Fletcher
3 days ago
I think the End Project Report would be more suitable in this situation.
upvoted 0 times
...
Alaine
4 days ago
D) Risk Register
upvoted 0 times
...
Allene
4 days ago
C) End Project Report
upvoted 0 times
...
Nathan
21 days ago
B) Exception Report
upvoted 0 times
...
Tracey
27 days ago
A) Benefits Review Plan
upvoted 0 times
...
Eloisa
1 months ago
B) Exception Report
upvoted 0 times
...
Melda
1 months ago
A) Benefits Review Plan
upvoted 0 times
...
...
Vicki
2 months ago
I think we should choose option C) End Project Report.
upvoted 0 times
...
Vanesa
2 months ago
The End Project Report seems like the appropriate choice here. It would capture all the key facts and highlight the impact of the competitors issuing calendars early.
upvoted 0 times
...

Save Cancel