Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PRINCE2 Exam PRINCE2-Practitioner Topic 1 Question 28 Discussion

Actual exam question for PRINCE2's PRINCE2-Practitioner exam
Question #: 28
Topic #: 1
[All PRINCE2-Practitioner Questions]

MANAGING PRODUCT DELIVERY

Stage 2 is in progress. While producing the team plan, the team manager responsible for the work package to develop the 'classroom-based training material' discovered that the representatives assigned to check the products were unsuitable.

Which action should the team manager take in response?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel