New Year Sale 2026! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PRINCE2-7-Foundation Exam - Topic 6 Question 6 Discussion

Actual exam question for PRINCE2's PRINCE2-7-Foundation exam
Question #: 6
Topic #: 6
[All PRINCE2-7-Foundation Questions]

Which statement about the 'manage by stages' principle is CORRECT?

Show Suggested Answer Hide Answer
Suggested Answer: B

The 'manage by stages' principle in PRINCE2 dictates that the end of each stage provides a control point at which the project board can review progress, reassess project viability, and decide on the next steps. This approach allows for regular monitoring and decision-making, ensuring that the project remains aligned with its objectives and within its tolerances. Reference: PRINCE2 7 Foundation guide on the 'manage by stages' principle.


Contribute your Thoughts:

0/2000 characters
Jimmie
3 months ago
B is the way to go, every stage needs a checkpoint!
upvoted 0 times
...
Lashawn
4 months ago
C seems off; shorter stages can help manage risk better.
upvoted 0 times
...
Sabrina
4 months ago
Wait, are we sure about A? That sounds risky!
upvoted 0 times
...
Francine
4 months ago
I think D makes more sense for clarity in projects.
upvoted 0 times
...
Mi
4 months ago
B is definitely correct! Control points are key.
upvoted 0 times
...
Mitsue
5 months ago
I thought that having separate stages for planning, delivering, and closing was important, but I can't recall if that's what the principle states.
upvoted 0 times
...
Wei
5 months ago
I feel like we practiced a question similar to this, and I think the project board definitely needs control points at the end of each stage, which sounds like B again.
upvoted 0 times
...
Charlene
5 months ago
I remember discussing how stages help manage risk, but I'm not sure if longer stages are better when risk is high.
upvoted 0 times
...
Gwen
5 months ago
I think the 'manage by stages' principle emphasizes control points, so maybe option B is correct?
upvoted 0 times
...
Carin
5 months ago
I'm pretty confident about this one. The 'manage by stages' principle is all about giving the project board control points to review progress and make decisions. So option B, where the end of a stage provides a control point, is the correct answer.
upvoted 0 times
...
Sabrina
5 months ago
Okay, I've got this. The 'manage by stages' principle is all about breaking the project down into smaller, more manageable chunks. So option D makes the most sense - a project should have separate stages to plan, deliver, and close.
upvoted 0 times
...
Davida
5 months ago
Hmm, I'm a bit confused by this question. I know the 'manage by stages' principle is important, but I'm not sure which of these options is correct. I might need to review my notes on that before answering.
upvoted 0 times
...
Rebecka
5 months ago
This is a tricky one. I'm not entirely sure about the 'manage by stages' principle, but I think option B sounds right - the end of a stage should provide a control point for the project board.
upvoted 0 times
...
Hailey
5 months ago
I'm a bit confused on this one. Placing a lock on a resource seems like it could fall under different roles, like User Access Administrator or Network Contributor. I'll need to review the permissions for each of these options to determine the best fit.
upvoted 0 times
...
Kanisha
5 months ago
Got it, the Velocity is 8 points since that's the total for the two completed and accepted stories. I'm ready to submit my answer.
upvoted 0 times
...
Aja
6 months ago
This seems like a straightforward question. I think the answer is to run the lsof command as root, since that would give me the complete report.
upvoted 0 times
...
Micah
6 months ago
I'm not entirely sure about this one. I'll make my best guess, but I may need to come back to it if I have time.
upvoted 0 times
...

Save Cancel