Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PRINCE2 Exam PRINCE2-7-Foundation Topic 5 Question 4 Discussion

Actual exam question for PRINCE2's PRINCE2-7-Foundation exam
Question #: 4
Topic #: 5
[All PRINCE2-7-Foundation Questions]

The project manager needs to record the impact assessment for a specific business opportunity.

In which management product should the project manager record this?

Show Suggested Answer Hide Answer
Suggested Answer: A

The project manager should record the impact assessment for a specific business opportunity in an 'Issue Report'. This management product is used to detail particular issues that might affect the project, including opportunities (which are treated like positive risks), and provides a basis for decision-making regarding these issues. Reference: PRINCE2 7 Foundation materials on issue management and related documentation.


Contribute your Thoughts:

Willow
10 months ago
Risk register all the way! That's where you keep track of all the things that could go wrong and how much they'll hurt if they do. Perfect place for an impact assessment.
upvoted 0 times
Marla
9 months ago
D) Quality register
upvoted 0 times
...
Jolanda
9 months ago
C) Risk register
upvoted 0 times
...
Rene
9 months ago
B) Issue register
upvoted 0 times
...
Cherry
10 months ago
A) Issue report
upvoted 0 times
...
Darrin
10 months ago
D) Quality register
upvoted 0 times
...
Juan
10 months ago
C) Risk register
upvoted 0 times
...
Donte
10 months ago
B) Issue register
upvoted 0 times
...
Louis
10 months ago
A) Issue report
upvoted 0 times
...
...
Providencia
11 months ago
This is a tough one. I'm going to have to go with C) Risk register. It just makes the most sense to me. Unless, of course, the project manager is feeling particularly risky today and wants to record it in the 'Danger Zone' register.
upvoted 0 times
...
Lore
11 months ago
I agree with Lottie, recording it in the Quality register makes the most sense.
upvoted 0 times
...
Lottie
11 months ago
I think it should be in the Quality register, as it impacts the overall quality of the project.
upvoted 0 times
...
Ming
11 months ago
The quality register seems like an odd choice. I'd go with the risk register - that's where you keep track of all the potential issues and their impacts.
upvoted 0 times
Val
10 months ago
I think the issue register could also work, but the risk register is more comprehensive.
upvoted 0 times
...
Rodolfo
10 months ago
I agree, the risk register is the best option for recording impact assessments.
upvoted 0 times
...
...
Marica
11 months ago
Hmm, I'm not so sure. Wouldn't the issue register be a more appropriate place to document this kind of impact assessment?
upvoted 0 times
...
Shizue
11 months ago
I think the risk register would be the best place to record the impact assessment. It's all about managing risks, right?
upvoted 0 times
Lorenza
10 months ago
Definitely, it helps to have a centralized location for all project-related assessments.
upvoted 0 times
...
Jacquelyne
10 months ago
I think it's important to have all the information in one place for easy reference.
upvoted 0 times
...
Beula
10 months ago
Yes, the risk register is specifically designed to manage and track risks.
upvoted 0 times
...
Evangelina
10 months ago
I agree, the risk register is the best place to record the impact assessment.
upvoted 0 times
...
Lawrence
10 months ago
D) Quality register
upvoted 0 times
...
Ivan
10 months ago
C) Risk register
upvoted 0 times
...
Vallie
10 months ago
B) Issue register
upvoted 0 times
...
Margurite
10 months ago
A) Issue report
upvoted 0 times
...
...
Kenny
11 months ago
I disagree, I believe it should be recorded in the Issue register.
upvoted 0 times
...
Maile
11 months ago
I think the project manager should record it in the Risk register.
upvoted 0 times
...

Save Cancel