PRINCE2-7-Foundation Exam - Topic 4 Question 28 Discussion

Actual exam question for PRINCE2's PRINCE2-7-Foundation exam
Question #: 28
Topic #: 4
[All PRINCE2-7-Foundation Questions]

Which statement defines a risk?

Show Suggested Answer Hide Answer
Suggested Answer: C

In PRINCE2, a risk is defined as any uncertain event or set of events that, if it occurs, will have an impact on the achievement of project objectives. This definition emphasizes the uncertainty and potential effect on objectives, rather than the certainty or immediate occurrence of an event. Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.


Contribute your Thoughts:

0/2000 characters
Michel
3 months ago
Wait, so B isn't a risk? That seems off.
upvoted 0 times
...
Ettie
3 months ago
I think A sounds more accurate. Negative impact is key.
upvoted 0 times
...
Nieves
3 months ago
Totally with C, it captures the essence of risk perfectly!
upvoted 0 times
...
Lindsey
3 months ago
D seems too specific, not all risks get escalated like that.
upvoted 0 times
...
Carmelina
4 months ago
Definitely C! It's all about uncertainty.
upvoted 0 times
...
Billy
4 months ago
I feel like D is too specific about escalation. Risks can happen without needing to escalate them immediately, so I think it's not the best choice.
upvoted 0 times
...
Santos
4 months ago
I'm a bit confused between A and C. A talks about a certain event, but I feel like risks are usually uncertain, right?
upvoted 0 times
...
Annamae
4 months ago
I remember practicing a question similar to this, and I think option C sounds right because it mentions uncertainty and effects on objectives.
upvoted 0 times
...
Chara
5 months ago
I think a risk is something uncertain, but I'm not sure if it's just about negative impacts or if it can also be positive.
upvoted 0 times
...
Derick
5 months ago
I'm confident that option A is too narrow, focusing only on negative impacts. Risks can have both positive and negative effects, so I don't think that's the best answer here.
upvoted 0 times
...
Annette
5 months ago
Option C seems to hit the nail on the head - an uncertain event that could affect project objectives. That's the classic definition of a risk, so I'm going with that one.
upvoted 0 times
...
Misty
5 months ago
Hmm, I'm a bit unsure about this one. The wording in the options seems similar, so I'll need to really focus on the key differences to pick the right answer.
upvoted 0 times
...
Kris
5 months ago
This looks like a straightforward definition question. I'll carefully read through the options and select the one that best matches the definition of a risk.
upvoted 0 times
...
Belen
8 months ago
Risks, risks, risks... sometimes I feel like they're the bane of a project manager's existence. But Option C is the right one, no doubt about it.
upvoted 0 times
Na
7 months ago
Risks can definitely be challenging to manage, but being prepared is key.
upvoted 0 times
...
Stephanie
7 months ago
I agree, Option C is definitely the correct definition of a risk.
upvoted 0 times
...
...
Pauline
8 months ago
As a project manager, I've had my fair share of risks. Option C is the way to go - it's the textbook definition of a risk.
upvoted 0 times
Kallie
7 months ago
User 2: Yeah, it's all about uncertain events that could impact our objectives.
upvoted 0 times
...
Vivan
7 months ago
User 1: I agree, option C is definitely the best definition of a risk.
upvoted 0 times
...
Precious
7 months ago
User 3: Absolutely, being prepared for those uncertainties is key in project management.
upvoted 0 times
...
Felix
7 months ago
User 2: I think so too, it's all about uncertain events that could impact the project.
upvoted 0 times
...
Azzie
8 months ago
User 1: I agree, option C is definitely the best definition of a risk.
upvoted 0 times
...
...
Ronny
8 months ago
The definition in Option C is spot on. Risks are about future uncertainty, not past events or automatic escalations.
upvoted 0 times
...
Graham
8 months ago
I'm not sure, but I think it's A. A risk is a certain event with negative impact.
upvoted 0 times
...
Torie
8 months ago
I agree with Thora. Option C captures the essence of a risk - an uncertain event that can affect the project's goals.
upvoted 0 times
Annamae
7 months ago
User 3: Definitely, we need to be prepared for those potential impacts.
upvoted 0 times
...
Mary
8 months ago
User 2: I agree, it's all about uncertain events that could impact the project.
upvoted 0 times
...
Maira
8 months ago
User 1: I think option C is the best definition of a risk.
upvoted 0 times
...
...
Kristofer
9 months ago
I agree with Pok, a risk is an uncertain event that could affect objectives.
upvoted 0 times
...
Pok
9 months ago
I think the answer is C.
upvoted 0 times
...
Thora
9 months ago
Option C seems to be the correct definition of a risk. Risks are uncertain events that can impact project objectives, not events that have already occurred or will be automatically escalated.
upvoted 0 times
Luke
8 months ago
It's important for project managers to identify and manage risks proactively.
upvoted 0 times
...
Lucy
9 months ago
Risks are indeed uncertain events that can affect project objectives.
upvoted 0 times
...
Joye
9 months ago
I agree, option C is the correct definition of a risk.
upvoted 0 times
...
...

Save Cancel