Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PRINCE2 Exam PRINCE2-7-Foundation Topic 4 Question 28 Discussion

Actual exam question for PRINCE2's PRINCE2-7-Foundation exam
Question #: 28
Topic #: 4
[All PRINCE2-7-Foundation Questions]

Which statement defines a risk?

Show Suggested Answer Hide Answer
Suggested Answer: C

In PRINCE2, a risk is defined as any uncertain event or set of events that, if it occurs, will have an impact on the achievement of project objectives. This definition emphasizes the uncertainty and potential effect on objectives, rather than the certainty or immediate occurrence of an event. Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.


Contribute your Thoughts:

Belen
29 days ago
Risks, risks, risks... sometimes I feel like they're the bane of a project manager's existence. But Option C is the right one, no doubt about it.
upvoted 0 times
Na
6 days ago
Risks can definitely be challenging to manage, but being prepared is key.
upvoted 0 times
...
Stephanie
7 days ago
I agree, Option C is definitely the correct definition of a risk.
upvoted 0 times
...
...
Pauline
1 months ago
As a project manager, I've had my fair share of risks. Option C is the way to go - it's the textbook definition of a risk.
upvoted 0 times
Vivan
10 days ago
User 1: I agree, option C is definitely the best definition of a risk.
upvoted 0 times
...
Precious
11 days ago
User 3: Absolutely, being prepared for those uncertainties is key in project management.
upvoted 0 times
...
Felix
12 days ago
User 2: I think so too, it's all about uncertain events that could impact the project.
upvoted 0 times
...
Azzie
1 months ago
User 1: I agree, option C is definitely the best definition of a risk.
upvoted 0 times
...
...
Ronny
1 months ago
The definition in Option C is spot on. Risks are about future uncertainty, not past events or automatic escalations.
upvoted 0 times
...
Graham
2 months ago
I'm not sure, but I think it's A. A risk is a certain event with negative impact.
upvoted 0 times
...
Torie
2 months ago
I agree with Thora. Option C captures the essence of a risk - an uncertain event that can affect the project's goals.
upvoted 0 times
Annamae
19 days ago
User 3: Definitely, we need to be prepared for those potential impacts.
upvoted 0 times
...
Mary
29 days ago
User 2: I agree, it's all about uncertain events that could impact the project.
upvoted 0 times
...
Maira
1 months ago
User 1: I think option C is the best definition of a risk.
upvoted 0 times
...
...
Kristofer
2 months ago
I agree with Pok, a risk is an uncertain event that could affect objectives.
upvoted 0 times
...
Pok
2 months ago
I think the answer is C.
upvoted 0 times
...
Thora
2 months ago
Option C seems to be the correct definition of a risk. Risks are uncertain events that can impact project objectives, not events that have already occurred or will be automatically escalated.
upvoted 0 times
Luke
2 months ago
It's important for project managers to identify and manage risks proactively.
upvoted 0 times
...
Lucy
2 months ago
Risks are indeed uncertain events that can affect project objectives.
upvoted 0 times
...
Joye
2 months ago
I agree, option C is the correct definition of a risk.
upvoted 0 times
...
...

Save Cancel