PRINCE2-7-Foundation Exam - Topic 3 Question 42 Discussion

Actual exam question for PRINCE2's PRINCE2-7-Foundation exam
Question #: 42
Topic #: 3
[All PRINCE2-7-Foundation Questions]

Which is an objective of the 'controlling a stage' process?

Show Suggested Answer Hide Answer
Suggested Answer: B

An objective of the 'Controlling a Stage' process in PRINCE2 is to replan the current stage when directed. This process handles day-to-day management of the project, and includes responding to issues that might impact the stage plan, requiring replanning to ensure project objectives can still be met. Reference: PRINCE2 Foundation Manual


Contribute your Thoughts:

0/2000 characters
Micheline
8 days ago
I feel like producing a learn plan for the work package could be relevant, but it seems more like a planning task than controlling.
upvoted 0 times
...
Rosina
13 days ago
I'm a bit confused; I thought developing products to defined quality criteria was more about the delivery phase than controlling a stage.
upvoted 0 times
...
Leigha
18 days ago
I remember practicing a question similar to this, and I think replanning the current stage is definitely part of it.
upvoted 0 times
...
Melvin
23 days ago
I think the objective of 'controlling a stage' might be about reviewing the business justification, but I'm not entirely sure.
upvoted 0 times
...