Which is an objective of the 'controlling a stage' process?
An objective of the 'Controlling a Stage' process in PRINCE2 is to replan the current stage when directed. This process handles day-to-day management of the project, and includes responding to issues that might impact the stage plan, requiring replanning to ensure project objectives can still be met. Reference: PRINCE2 Foundation Manual