MultipleChoice
A software development project completed the initiation phase. The technical design was approved by the project steering committee. Later, it was discovered that the design will impact the company's production system. A new technical design must be found and this could delay the project by 3 months.
What should the project manager do first?
OptionsMultipleChoice
A project team consisting of 13 people was set up three months ago. As part of the transition to agile, a scrum master was assigned to the project. The scrum master wants to know the status of the team's development stage. The project manager believes that the team has passed the "storming" stage.
Which indicators should be used to determine the team's development stage?
OptionsMultipleChoice
A project manager analyzes the cumulative flow chart and identifies a bottleneck in the testing activities from a self-organizing team. After discussing it with the team, a gap related to testing skills is identified.
What should the project manager do to address the issue?
OptionsMultipleChoice
A project team is prioritizing the creation of project artifacts and enforcing it rigidly, while they face issues with delays in deliverables. How should the project manager respond?
OptionsMultipleChoice
A project is starting its first iteration out of six. During one of the daily meetings, the project manager realized that one of the team members does not have experience working in agile environments.
What should the project manager do?
OptionsMultipleChoice
An experienced team member has recently started performing at a slower pace and is no longer engaged in various team conversations. What should the project manager do?
OptionsMultipleChoice
A project manager and project team are developing a strategic approach to engage the internal and external stakeholders. Which approach should be followed?
OptionsMultipleChoice
A company has an existing contract to maintain and enhance a client's customer database The company's legal department informs the project manager that a new piece of legislature requiring stricter protection of customer information might soon be signed into law. The law will require additional security features to be implemented into the database the project manager is maintaining These features are not included in the scope of the current contract
What should the project manager do?
OptionsDragDrop
Drag the interpersonal skill on the left to the correct scenario on the right.

















MultipleChoice
A project is nearing completion. The contingency time has been consumed. To ensure that the final deliverables are achieved on time and within budget, the
project manager has asked the team to follow a rigorous process. This is causing some resistance among the team members.
What should the project manager do to address the growing resistance?
Options