PMI PMP Exam - Topic 3 Question 7 Discussion
During a documentation audit of an international company it was identified that the last version of the project schedule was from one month ago even though the project manager knew it was recently updated How should the project manager have handled documentation for the project?
A) Updated the project management plan regularly and had it securely shared with all stakeholders
B) Assigned a project team member to ensure all project documentation was updated
C) Reviewed the risk register to identify a response plan for the audit
D) Kept documentation in the project management information system (PMIS), and shared it with appropriate stakeholders
Cornell
10 months agoChristoper
11 months agoSabrina
11 months agoTimothy
11 months agoDaniel
11 months agoKerry
11 months agoKeena
11 months agoSophia
11 months agoArthur
11 months agoCarylon
12 months agoDona
12 months agoOdette
12 months agoJesus
12 months ago