PMI PMP Exam - Topic 3 Question 61 Discussion
During iteration planning, team A identifies that an important deliverable is dependent upon a deliverable from team B. What should the project manager do?
A) Inform team B of the dependency and ensure that the deliverable is planned.
B) Make team Aa part of team B and ensure that the deliverable is ready.
C) Request team B to immediately start this activity and deliver to team A.
D) Ask team B to focus on their backlog and deliver based on their priority,