PMI PMP Exam - Topic 3 Question 55 Discussion
A project manager leads a software development project in a hybrid environment. During project planning, the project manager identified a risk where a technical resourcefor a critical path item may not be available when needed. One week before the resource is needed, the technical engineer had a personal emergency and had to take aleave.What should the project manager do next?
C) Consult the risk register for an appropriate planned risk response and implement.
A) Update the lessons learned report and the risk log to reflect that this risk has materialized.
B) Revise the project management plan and move the task to a time when the technical resource will be available.
D) Review the business requirement with stakeholders and exclude the task assigned to the technical resource.
Milly
7 months agoMari
7 months agoDianne
7 months agoVirgina
8 months agoPortia
8 months agoJohnetta
8 months agoGladys
8 months agoPauline
8 months agoAlpha
8 months agoJaclyn
8 months agoRosalyn
8 months agoMitzie
8 months agoValene
8 months ago