PMI PMP Exam - Topic 3 Question 3 Discussion

A project manager notices that the project is behind schedule because materials delivery was delayed. The procurement team informs the project manager that new government-imposed rules for the procurement of these materials caused this delay.In what plan should these new rules be documented?
D) Procurement management
A) Project management
B) Communications management
C) Stakeholder engagement

PMI PMP Exam - Topic 3 Question 3 Discussion

Actual exam question for PMI's PMP exam
Question #: 3
Topic #: 3
[All PMP Questions]

A project manager notices that the project is behind schedule because materials delivery was delayed. The procurement team informs the project manager that new government-imposed rules for the procurement of these materials caused this delay.

In what plan should these new rules be documented?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

0/2000 characters
Brinda
7 months ago
I thought it might fit in Communications management too.
upvoted 0 times
...
Timothy
7 months ago
100% D. Can't overlook the impact of regulations!
upvoted 0 times
...
Beth
7 months ago
Wait, are we sure it's just the new rules causing the delay?
upvoted 0 times
...
Olive
8 months ago
Agreed, that's where it belongs!
upvoted 0 times
...
Sherman
8 months ago
Definitely in the Procurement management plan.
upvoted 0 times
...
Sharen
8 months ago
I keep second-guessing myself, but I wonder if it could also relate to communications management since we need to inform stakeholders about the changes.
upvoted 0 times
...
Suzi
8 months ago
This seems similar to a practice question we did on procurement delays. I feel like the answer is definitely related to procurement management.
upvoted 0 times
...
Altha
8 months ago
I'm not entirely sure, but I remember something about documenting changes in the project management plan too.
upvoted 0 times
...
Zachary
8 months ago
I think the new rules should go in the procurement management plan since they directly affect how we acquire materials.
upvoted 0 times
...
Edna
8 months ago
I'm pretty sure residual income is used to evaluate investment centres, so I'll go with option C.
upvoted 0 times
...
Kristal
8 months ago
This question seems straightforward. I think the key is to focus on the term "screening" and what that means in the context of prospective drug utilization review.
upvoted 0 times
...
Sherita
8 months ago
Hmm, I'm not totally sure about this one. I'll have to think it through carefully.
upvoted 0 times
...
Chan
8 months ago
I've got a good feeling about B for this one. The primary purpose of an EI is to maintain one or more ILFs, which is what option B states. I'm confident in that answer.
upvoted 0 times
...
Marguerita
8 months ago
Honestly, I'm confused. I thought risks should be monitored continuously throughout the process, but I can't remember where that fits in order.
upvoted 0 times
...
Alexis
8 months ago
Hmm, the part about not being able to return to the question is a bit tricky. I'll need to make sure I have the full picture before answering.
upvoted 0 times
...

Save Cancel