New Year Sale 2026! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI PMP Exam - Topic 3 Question 28 Discussion

Actual exam question for PMI's PMP exam
Question #: 28
Topic #: 3
[All PMP Questions]

A company has agreed to run a transformation project using agile approaches.

During the implementation, there is pushback from the functional groups that the project is moving too fast.

What should the project manager have done at the beginning of the project to prevent this from happening?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

0/2000 characters
Felix
4 months ago
Agree, understanding the culture can prevent a lot of pushback!
upvoted 0 times
...
Tenesha
4 months ago
Not sure if circulating the project charter would have helped much.
upvoted 0 times
...
Mike
4 months ago
Surprised they didn't consider employee maturity levels from the start.
upvoted 0 times
...
Nenita
4 months ago
I think communicating the project schedule is key too!
upvoted 0 times
...
Weldon
4 months ago
Definitely should have assessed the organizational culture first.
upvoted 0 times
...
Nu
5 months ago
Communicating the project schedule sounds important, but I wonder if it would really address the pushback from functional groups.
upvoted 0 times
...
Mitzie
5 months ago
I remember a practice question about employee maturity levels. Maybe understanding that could have eased the transition?
upvoted 0 times
...
Cherelle
5 months ago
I'm not sure if circulating the project charter would have helped. It seems more about getting buy-in from the start.
upvoted 0 times
...
Denae
5 months ago
I think assessing the organizational culture is crucial. If the team isn't ready for agile, it could lead to issues like this.
upvoted 0 times
...
Vallie
5 months ago
Honestly, I'm a bit confused by this question. Isn't Amazon S3 supposed to be super durable? Why would we need to confirm the data was inserted at all?
upvoted 0 times
...
Salina
5 months ago
Hmm, this seems like it could be a tricky one. I'll need to think through the different directories and their purposes in the Oracle VM environment. Let me see if I can eliminate some of the options first.
upvoted 0 times
...
Rene
5 months ago
This seems straightforward to me. Based on the object types shown, I believe the correct answer is User1 and Guest1 only, since those are the user-type objects that can be assigned roles in Azure PIM.
upvoted 0 times
...

Save Cancel