PMI PMP Exam - Topic 3 Question 19 Discussion
During a meeting to define project scope a stakeholder tells the project manager that the main requested feature in the contract is not applicable, and this is documented m the lessons learned. What should the project manager do?
A) Check with the team to learn what can be done, and consult an expert
B) Ask the sponsor to close the project and pay the contracted penalty.
C) Check that this information was documented correctly
D) Meet with the sponsor to ask for their support
Youlanda
10 months agoVenita
11 months agoKristel
11 months agoMertie
11 months agoMaryrose
11 months agoDorsey
11 months agoReynalda
11 months agoTran
11 months agoJohnetta
11 months agoAlesia
12 months agoNorah
12 months agoPrincess
12 months agoRosio
12 months ago