Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI PMP Exam - Topic 3 Question 19 Discussion

During a meeting to define project scope a stakeholder tells the project manager that the main requested feature in the contract is not applicable, and this is documented m the lessons learned. What should the project manager do?
A) Check with the team to learn what can be done, and consult an expert
B) Ask the sponsor to close the project and pay the contracted penalty.
C) Check that this information was documented correctly
D) Meet with the sponsor to ask for their support

PMI PMP Exam - Topic 3 Question 19 Discussion

Actual exam question for PMI's PMP exam
Question #: 19
Topic #: 3
[All PMP Questions]

During a meeting to define project scope a stakeholder tells the project manager that the main requested feature in the contract is not applicable, and this is documented m the lessons learned. What should the project manager do?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

0/2000 characters
Youlanda
7 months ago
I’m not sure about option B, closing the project seems extreme!
upvoted 0 times
...
Venita
7 months ago
Option D could work too, getting the sponsor involved is smart.
upvoted 0 times
...
Kristel
7 months ago
Wait, how can a feature be in the contract but not applicable? Sounds fishy.
upvoted 0 times
...
Mertie
8 months ago
Totally agree, checking the documentation is key!
upvoted 0 times
...
Maryrose
8 months ago
I think option C is the best choice. Always verify documentation first.
upvoted 0 times
...
Dorsey
8 months ago
I feel like asking the sponsor to close the project might be too drastic. Maybe we should explore other options first?
upvoted 0 times
...
Reynalda
8 months ago
I'm not entirely sure, but I think checking with the team could help clarify the situation, like in that practice scenario we did.
upvoted 0 times
...
Tran
8 months ago
I remember something about verifying documentation before making decisions, so option C seems like a good first step.
upvoted 0 times
...
Johnetta
8 months ago
I vaguely recall that meeting with the sponsor could be important, but I wonder if we should confirm the lesson learned first.
upvoted 0 times
...
Alesia
8 months ago
Hmm, I'm not too familiar with the different provider IDs out there. I'll need to think this through carefully.
upvoted 0 times
...
Norah
8 months ago
I think option B is the way to go here. The question specifically says we need to display the pipeline run details written to the STDOUT output, and the `wait_for_completion(show_output=True)` method should do the trick.
upvoted 0 times
...
Princess
8 months ago
I'm a bit confused on the "ExchStart" state - I'll need to review my OSPF notes to refresh my memory on what that means exactly.
upvoted 0 times
...
Rosio
8 months ago
This looks like a networking or web application issue. I'll need to carefully review the HTTP headers and request details to determine the root cause.
upvoted 0 times
...

Save Cancel