PMI PMP Exam - Topic 3 Question 19 Discussion
During a meeting to define project scope a stakeholder tells the project manager that the main requested feature in the contract is not applicable, and this is documented m the lessons learned. What should the project manager do?
A) Check with the team to learn what can be done, and consult an expert
B) Ask the sponsor to close the project and pay the contracted penalty.
C) Check that this information was documented correctly
D) Meet with the sponsor to ask for their support
Youlanda
7 months agoVenita
7 months agoKristel
7 months agoMertie
8 months agoMaryrose
8 months agoDorsey
8 months agoReynalda
8 months agoTran
8 months agoJohnetta
8 months agoAlesia
8 months agoNorah
8 months agoPrincess
8 months agoRosio
8 months ago