PMI PMP Exam - Topic 3 Question 15 Discussion
A self-organizing team was delivering as committed. The team accepted a development task with new technology and the iterations started to have reduced velocity. What management decision is suited for this situation?
A) Provide opportunity for team members to learn and adjust to the technology.
B) Move team members who are not performing from the team.
C) Add new members to the team and increase the velocity
D) Re-assign the project to a team that has worked with this technology
Billye
10 months agoViva
11 months agoLavera
11 months agoLou
11 months agoGretchen
11 months agoJonelle
11 months agoKristofer
11 months agoShala
11 months agoLatonia
11 months agoAlonzo
12 months agoHuey
12 months agoGlendora
12 months agoRodolfo
12 months ago