PMI PMP Exam - Topic 3 Question 15 Discussion
A self-organizing team was delivering as committed. The team accepted a development task with new technology and the iterations started to have reduced velocity. What management decision is suited for this situation?
A) Provide opportunity for team members to learn and adjust to the technology.
B) Move team members who are not performing from the team.
C) Add new members to the team and increase the velocity
D) Re-assign the project to a team that has worked with this technology
Billye
7 months agoViva
7 months agoLavera
7 months agoLou
8 months agoGretchen
8 months agoJonelle
8 months agoKristofer
8 months agoShala
8 months agoLatonia
8 months agoAlonzo
8 months agoHuey
8 months agoGlendora
8 months agoRodolfo
8 months ago