PMI PMP Exam - Topic 3 Question 114 Discussion

Posted by Marti on Apr 06, 2026 at 12:18 PM

During the execution of a project within an operations function the project manager encounters scope changes and a delay in the delivery of critical tasks How should the project manager address this situation?

Suggested Answer: C

The project manager should initiate the change request to modify the scope and adjust the timelines. This is because the project manager is responsible for managing the project scope and ensuring that the project delivers the agreed outcomes within the approved budget and schedule. When the project manager encounters scope changes and a delay in the delivery of critical tasks, they should follow the change management process as defined in the project management plan. This process involves initiating a change request that describes the proposed changes, their impact, and their justification. The change request should then be submitted to the appropriate authority, such as the change control board or the steering committee, for review and approval. The project manager should also update the project documents, such as the scope baseline, the schedule baseline, and the cost baseline, to reflect the approved changes. The project manager should communicate the changes and their implications to the relevant stakeholders, such as the project team, the PMO, the sponsor, and the customer.Reference:PMBOK Guide, 6th edition, section 4.6, page 115,PMP Exam Prep, 10th edition, page 180


Get Premium PMP Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
21 comments · newest first
MA
Marlon 2 months ago
C seems practical. We need to adjust timelines ASAP.
LO
Louisa 2 months ago
I feel D is the most thorough approach. Steering committee needs to know.
DO
Dortha 2 months ago
B could work, but it might delay things more.
CH
Chaya 2 months ago
A is good too. Keeping PMO in the loop is crucial.
GR
Gretchen 3 months ago
I prefer D. Impact analysis gives a clear picture.
JE
Jess 3 months ago
I think option C is the best. Change requests are essential.
FI
Filiberto 3 months ago
C is clear and direct. We need to adjust timelines right away.
RE
Regenia 3 months ago
I prefer D. Steering committee needs to know the full impact.
DE
Detra 3 months ago
A team meeting could help. We need everyone's input on changes.
RA
Rashad 3 months ago
A weekly report to PMO? Seems too slow for urgent issues.
IR
Irene 4 months ago
I agree, but option D sounds good too. Impact analysis is crucial.
SH
Shelia 4 months ago
I think option C is the best. Changes need formal approval.
MI
Ming 4 months ago
Totally agree, the steering committee should be involved for approval.
QU
Quentin 4 months ago
Wait, how can we trust the impact analysis will be accurate?
AL
Alberta 4 months ago
Change requests are a must in this situation!
LA
Lavelle 6 months ago
I think a team meeting is crucial to get everyone on the same page.
AR
Arlette 6 months ago
Definitely need to communicate with the PMO first.
SH
Shanda 7 months ago
Option C seems a bit rushed to me. I feel like we should assess the situation more thoroughly before initiating a change request.
GA
Galen 7 months ago
I remember a practice question where we had to decide on scope changes, and I think calling a team meeting like in option B could be useful to get everyone's input.
NA
Na 7 months ago
I'm not really sure if we should go straight to the PMO with option A. It feels like we should handle it internally first.
MA
Marge 7 months ago
I think option D makes the most sense since conducting an impact analysis could help understand the full effects of the changes.