New Year Sale 2026! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI PMP Exam - Topic 2 Question 93 Discussion

Actual exam question for PMI's PMP exam
Question #: 93
Topic #: 2
[All PMP Questions]

A recently concluded quality audit failed and came back with multiple action items. A newly appointed project manager is reviewing the project status with the team. New stakeholders have been identified, and new audit resources may have to be added to the project.

What should the project manager do next?

Show Suggested Answer Hide Answer
Suggested Answer: B

When faced with the aftermath of a failed quality audit, the newly appointed project manager must take several steps to address the situation. Let's explore the options:

1. Perform Integrated Change Control (Option B):

o Integrated change control is a critical process in project management.

o It involves reviewing all change requests, assessing their impact, and making informed decisions about whether to approve or reject them.

o In this case, the failed audit results constitute a change request. The project manager should evaluate the impact of the audit findings, identify necessary corrective actions, and determine whether additional resources (such as new audit resources) are required.

o By performing integrated change control, the project manager ensures that any necessary adjustments are made to the project plan, scope, schedule, and resources.

2. Stakeholder Engagement (Option A):

o While stakeholder engagement is essential, it is not the immediate next step after a failed audit.

o Stakeholder engagement involves ongoing communication and collaboration with stakeholders throughout the project lifecycle.

o The project manager should engage stakeholders, but addressing the audit findings takes precedence.

3. Update the Quality Management Plan (Option C):

o Updating the quality management plan is relevant, but it is a specific response to the audit results.

o The project manager should first assess the impact of the audit findings and then update the quality management plan as needed.

4. Update the Risk Management Plan (Option D):

o While risk management is crucial, it is not the immediate focus after a failed audit.

o The project manager should address the audit findings before revisiting the risk management plan.

In summary, the project manager should prioritize integrated change control to address the audit results, identify corrective actions, and


Contribute your Thoughts:

0/2000 characters
Corinne
3 months ago
Totally agree, engaging stakeholders first makes sense!
upvoted 0 times
...
Theola
3 months ago
Wait, are we sure adding new resources is the right move?
upvoted 0 times
...
Princess
3 months ago
Definitely need to perform integrated change control!
upvoted 0 times
...
Hailey
4 months ago
I think updating the quality management plan is more important.
upvoted 0 times
...
Izetta
4 months ago
Stakeholder engagement is key here!
upvoted 0 times
...
Wilda
4 months ago
I wonder if updating the risk management plan is necessary here. It might help address new risks from the audit findings, but I’m not sure if it’s the priority right now.
upvoted 0 times
...
Odelia
4 months ago
I keep thinking about integrated change control. It seems like a logical step after a failed audit, but I’m not confident if it’s the first thing to do.
upvoted 0 times
...
Louvenia
4 months ago
I'm not entirely sure, but I feel like updating the quality management plan could be important too. We discussed how quality issues often lead to changes in project plans.
upvoted 0 times
...
Aja
5 months ago
I think the project manager should focus on stakeholder engagement first. I remember a practice question where identifying stakeholders was crucial after a major audit.
upvoted 0 times
...
Stefanie
5 months ago
Okay, let's see. Since the quality audit failed, I'd say updating the quality management plan is the logical next step. That will help us address the issues identified and get the project back on track.
upvoted 0 times
...
Gilbert
5 months ago
Hmm, this is a tricky one. With new stakeholders and audit resources, I think the key is to focus on managing the changes to the project. Integrated change control seems like the way to go here.
upvoted 0 times
...
Stevie
5 months ago
I'm a bit unsure here. There are a few different options that could work, like updating the quality or risk management plans. I'll need to think through the details of each approach to decide which one is best.
upvoted 0 times
...
Thurman
5 months ago
This seems like a straightforward project management question. I'd start by looking at the stakeholder engagement process to make sure we have the right people involved and their needs are being addressed.
upvoted 0 times
...
Nathan
1 year ago
I'm feeling a bit like a quality auditor myself, trying to figure out the right answer here. Maybe we need to add some comic relief to this serious project management question!
upvoted 0 times
...
Luke
1 year ago
Hmm, B) Perform integrated change control seems like the way to go. The new stakeholders and audit resources are likely to introduce changes that need to be managed.
upvoted 0 times
Clarence
1 year ago
B) Perform integrated change control.
upvoted 0 times
...
Tashia
1 year ago
A) Perform stakeholder engagement.
upvoted 0 times
...
...
Cammy
1 year ago
I'm going with C) Update the quality management plan. The failed audit suggests the need to review and update the quality processes.
upvoted 0 times
Hobert
1 year ago
D: We should definitely perform integrated change control to address any changes that need to be made as a result of the audit findings.
upvoted 0 times
...
Argelia
1 year ago
C: Updating the quality management plan is crucial to ensure that we meet the required quality standards.
upvoted 0 times
...
Louis
1 year ago
B: I agree, it's important to address any potential risks that were identified during the audit.
upvoted 0 times
...
Amie
1 year ago
A: I think we should also consider updating the risk management plan.
upvoted 0 times
...
...
Luann
1 year ago
I believe performing integrated change control (B) is also important to ensure all changes are properly managed in light of the audit results.
upvoted 0 times
...
Fausto
1 year ago
I agree with Judy. Updating the quality management plan is crucial to address the action items from the audit.
upvoted 0 times
...
Judy
1 year ago
I think the project manager should update the quality management plan (C) because the audit failed.
upvoted 0 times
...
Isidra
1 year ago
D) Update the risk management plan seems like the appropriate choice here. The project manager needs to assess the risks and update the plan accordingly.
upvoted 0 times
Eliseo
1 year ago
C: Let's make sure to involve the new stakeholders in the process as well to ensure their input is considered.
upvoted 0 times
...
Joesph
1 year ago
B: Agreed, that would help us mitigate any potential risks moving forward.
upvoted 0 times
...
Lonna
1 year ago
A: I think we should update the risk management plan to address the issues highlighted in the audit.
upvoted 0 times
...
...
Louvenia
1 year ago
I think the answer is A) Perform stakeholder engagement. The new stakeholders need to be identified and engaged to address the issues from the failed audit.
upvoted 0 times
Basilia
1 year ago
D: Updating the risk management plan is important to address any new risks that may arise from the failed audit.
upvoted 0 times
...
Vivan
1 year ago
C: I think performing integrated change control could help us manage the new audit resources effectively.
upvoted 0 times
...
Lenna
1 year ago
B: We should also consider updating the quality management plan to ensure we meet the audit requirements.
upvoted 0 times
...
Lisbeth
1 year ago
A: I agree, engaging the new stakeholders is crucial for addressing the audit issues.
upvoted 0 times
...
...

Save Cancel