PMI PMP Exam - Topic 2 Question 84 Discussion
A project manager is using a hybrid approach for project delivery. Thedevelopment team was sized, but is not yet fully resourced. The project manager is workingon defining the project schedule.What should the project manager do to address the issue of developer availability?
B) Ask the resource manager when the new contractor is available to start and change the delivery date for the project schedule.
A) Organize a planning session with the development team and use their estimations to complete the schedule.
C) Ask the sponsor to provide the desired completion date for project activities and complete the schedule.
D) Use expert judgment to estimate all of the tasks and complete the schedule in the allocated time.
Paulina
6 months agoMarquetta
6 months agoTommy
7 months agoJoanne
7 months agoKarl
7 months agoAlonzo
7 months agoSabine
8 months agoBuffy
8 months agoDalene
8 months agoMarkus
8 months agoFidelia
8 months agoSvetlana
8 months agoZack
8 months agoLavera
8 months agoEzekiel
8 months agoTammara
8 months agoCassi
1 year agoGwen
11 months agoHillary
12 months agoFletcher
1 year agoLindsay
1 year agoLeoma
1 year agoPhil
12 months agoOliva
1 year agoWilda
1 year agoLavera
1 year agoLouvenia
1 year agoKris
1 year agoAleta
1 year agoNelida
1 year agoJuan
1 year agoGail
1 year agoAzalee
1 year agoMing
1 year agoLeatha
1 year agoGiuseppe
1 year ago