PMI PMP Exam - Topic 2 Question 84 Discussion
A project manager is using a hybrid approach for project delivery. Thedevelopment team was sized, but is not yet fully resourced. The project manager is workingon defining the project schedule.What should the project manager do to address the issue of developer availability?
B) Ask the resource manager when the new contractor is available to start and change the delivery date for the project schedule.
A) Organize a planning session with the development team and use their estimations to complete the schedule.
C) Ask the sponsor to provide the desired completion date for project activities and complete the schedule.
D) Use expert judgment to estimate all of the tasks and complete the schedule in the allocated time.
Paulina
10 months agoMarquetta
10 months agoTommy
10 months agoJoanne
10 months agoKarl
11 months agoAlonzo
11 months agoSabine
11 months agoBuffy
11 months agoDalene
11 months agoMarkus
11 months agoFidelia
11 months agoSvetlana
11 months agoZack
11 months agoLavera
12 months agoEzekiel
12 months agoTammara
12 months agoCassi
1 year agoGwen
1 year agoHillary
1 year agoFletcher
1 year agoLindsay
1 year agoLeoma
1 year agoPhil
1 year agoOliva
1 year agoWilda
1 year agoLavera
1 year agoLouvenia
1 year agoKris
1 year agoAleta
1 year agoNelida
1 year agoJuan
1 year agoGail
1 year agoAzalee
1 year agoMing
1 year agoLeatha
1 year agoGiuseppe
1 year ago