Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMP Topic 2 Question 84 Discussion

Actual exam question for PMI's PMP exam
Question #: 84
Topic #: 2
[All PMP Questions]

A project manager is using a hybrid approach for project delivery. The

development team was sized, but is not yet fully resourced. The project manager is working

on defining the project schedule.

What should the project manager do to address the issue of developer availability?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Cassi
8 days ago
I bet the project manager is wishing they had a crystal ball to see the future and know exactly when those contractors will be available!
upvoted 0 times
...
Lindsay
16 days ago
Using expert judgment to estimate everything sounds like a recipe for disaster. This is a hybrid project, so the team's input is essential.
upvoted 0 times
...
Leoma
20 days ago
Asking the sponsor for the desired completion date is a bit backwards. The schedule should be built from the bottom up, not dictated from the top down.
upvoted 0 times
Wilda
10 days ago
A) Organize a planning session with the development team and use their estimations to complete the schedule.
upvoted 0 times
...
...
Lavera
1 months ago
Asking the resource manager about contractor availability is a good idea, but it shouldn't be the only factor in defining the schedule. The team's expertise is key here.
upvoted 0 times
Louvenia
21 days ago
B) Asking the resource manager is important, but getting input from the development team is crucial for accuracy.
upvoted 0 times
...
Kris
22 days ago
A) Organize a planning session with the development team and use their estimations to complete the schedule.
upvoted 0 times
...
...
Aleta
1 months ago
The project manager should definitely organize a planning session with the development team. They know best how long the tasks will take, and their input is crucial for an accurate schedule.
upvoted 0 times
Nelida
2 days ago
C) Asking the sponsor for the desired completion date may not be the best approach without consulting the development team first.
upvoted 0 times
...
Juan
10 days ago
A) It's important to involve the team in the planning process to ensure realistic timelines.
upvoted 0 times
...
Gail
12 days ago
B) That sounds like a good idea. The development team's input is important for accurate scheduling.
upvoted 0 times
...
Azalee
20 days ago
A) Organize a planning session with the development team and use their estimations to complete the schedule.
upvoted 0 times
...
...
Ming
2 months ago
But what if the new contractor's availability affects the project timeline? Shouldn't we consider that too?
upvoted 0 times
...
Leatha
2 months ago
I agree with Giuseppe, using the team's estimations will help in completing the schedule.
upvoted 0 times
...
Giuseppe
2 months ago
I think the project manager should organize a planning session with the development team.
upvoted 0 times
...

Save Cancel