PMI PMP Exam - Topic 2 Question 63 Discussion
A project manager is part of a balanced matrix project organization. The project manager will receive all work performance updates directly from the new sourcingdepartment head who has no time to spare to give the project manager the information.What should the project manager do?
A) Request information directly from the sourcing department team members.
B) Present the situation to the manager of the sourcing department head.
C) Discuss the situation with the company project sponsor for advice.
D) Work out a resolution in consultation with the sourcing department head.