PMI PMP Exam - Topic 2 Question 37 Discussion
During the sprint planning of a project, the team members have a disagreementabout the comparative size of the backlog items and if they would fit into the next sprint.Considering a hybrid approach, what should the project manager do?
D) Facilitate the discussion so that the team members can reach a consensus.
A) Ask an external technical leader to provide input and plan the sprint.
B) Remove the items from the product backlog since the size couldn't be estimated.
C) Make the decision about the backlog items based on what makes more sense.