PMI PMP Exam - Topic 2 Question 30 Discussion
A product owner has provided the team with a prioritized backlog for the initiallaunch of a new product. After analysis, the team concludes that some work is missing tosupport the initial launch and provides this information to the product owner. The productowner acknowledges the missing work and adds it to the bottom of the backlog. The team isnot happy with the prioritization that the missing work received.What should the project manager do in this situation?
C) Recommend the product owner prioritize the missing work higher because it is
needed for the minimum viable product (MVP).
A) Let the project team pull the recommended work from the bottom of the backlog to
maximize value creation.
B) Analyze and reprioritize the backlog and provide the decision to the product owner
and team.
D) Empower the product owner by supporting the decision and instructing the team to follow the prioritization as provided.
Hoa
7 months agoMozell
7 months agoMitzie
7 months agoSolange
8 months agoAudry
8 months agoRose
8 months agoKendra
8 months agoHelene
8 months agoHollis
8 months agoBerry
8 months agoChaya
8 months agoPenney
8 months agoElmira
8 months ago