A large organization decided to adopt an agile methodology based on the trendsseen in the industry. The organization invested a large amount of money in adopting it, butafter a few months, the implementation failed.What should the project manager have done differently to avoid the implementation failure?
C) Assessed the organization's culture, performed a suitability analysis, and determined
the future state.
A) Conducted agile training for all employees ranging from the project teams through
mid-level to upper-level management.
B) Conducted a postmortem and captured the learning in organizational process assets
(OPAs) for future use.
D) Hired a third-party agile delivery team to do the implementation.