PMI PMP Exam - Topic 2 Question 23 Discussion

Posted by Alease on May 05, 2022 at 05:13 AM

A project using a hybrid approach to migrate from a current system to a new and

enhanced system is underway. The plan is to migrate the system in stages. However, the

operations team is complaining that they are not ready to start supporting the new system.

How should the project manager effectively approach this situation?

Suggested Answer: B

Get Premium PMP Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
12 comments · newest first
KE
Kenda 1 year ago
D is nice, but documentation alone won't cut it.
AL
Aliza 1 year ago
Totally agree with B! We need to bridge that gap.
CA
Catina 1 year ago
Wait, are they really not ready? How did that happen?
LA
Latricia 1 year ago
A lesson learned register sounds good, but it won't help now.
SE
Selma 1 year ago
I think B is the best option. Knowledge transfer is key!
MY
Myrtie 1 year ago
Changing the project management plan to add a final stage, like in option C, could work, but it might delay the project. I’m not convinced that’s the best approach.
MA
Malcom 1 year ago
I think we practiced a question similar to this, and I remember that including the operations team early on was emphasized. So, option B seems like a solid choice.
BE
Beata 1 year ago
I'm not entirely sure, but I feel like just creating documentation at the end, like in option D, might not be enough. The operations team needs to be prepared before the final handoff.
MA
Malcom 1 year ago
I remember discussing the importance of knowledge transfer in our last class. I think option B makes the most sense since it ensures the operations team is involved throughout the process.
LE
Leanna 1 year ago
Hmm, this seems like a tricky one. I'll need to carefully review the options and think through the potential issues with the custom object.
JE
Jeannine 1 year ago
This seems like a pretty straightforward question about the responsibilities of a business relationship manager. I think I have a good handle on the key points, so I'll try to outline the best approach.
RO
Royal 1 year ago
I think option A makes the most sense. We need to collect user data to really understand their needs, but I'm not sure if "define" is the right word—maybe "refine" would fit better?