PMI PMP Exam - Topic 2 Question 18 Discussion
A team is working on a project using a hybrid approach, and they are facing a lot of obstacles and blockers from some stakeholders. What should the project manager do to improve project performance?
C) Address and remove obstacles and blockers for the team
A) Ask stakeholders to communicate with the project manager and not directly with the team
B) Empower the team members to remove obstacles and blockers
D) Add blockers to the issue log and risk management plan