PMI PMP Exam - Topic 1 Question 56 Discussion
A project manager noticed that the functional manager is not cooperating with staff assignment schedules and is always finding excuses not fo release the requested staff.What should the project manager do first?
C) Have a direct talk with the functional manager to understand the reasons behind their attitude.
A) Ask the leadership team for help obtaining the needed staff.
B) Check with human resources (HR) regarding the availability of staff.
D) Evaluate the impact caused by the delay of forming the team and confront the functional manager.
Precious
10 months agoMaile
11 months agoJohnna
11 months agoStephania
11 months agoBong
11 months agoJose
11 months agoLai
11 months agoMarleen
11 months agoYvonne
11 months agoLang
12 months agoMa
12 months agoLai
12 months ago