PMI PMP Exam - Topic 1 Question 56 Discussion
A project manager noticed that the functional manager is not cooperating with staff assignment schedules and is always finding excuses not fo release the requested staff.What should the project manager do first?
C) Have a direct talk with the functional manager to understand the reasons behind their attitude.
A) Ask the leadership team for help obtaining the needed staff.
B) Check with human resources (HR) regarding the availability of staff.
D) Evaluate the impact caused by the delay of forming the team and confront the functional manager.
Precious
7 months agoMaile
7 months agoJohnna
7 months agoStephania
8 months agoBong
8 months agoJose
8 months agoLai
8 months agoMarleen
8 months agoYvonne
8 months agoLang
8 months agoMa
8 months agoLai
8 months ago