A project manager noticed that the functional manager is not cooperating with staff assignment schedules and is always finding excuses not fo release the requested staff.
What should the project manager do first?
Suggested Answer: C
Get Premium PMP Questions
as Interactive Web-Based Practice Test or PDF
Real Exam Format
Detailed Explanations
Instant Access
Get Your Practice Test
12 comments · newest first
PR
Precious
12 months ago
Confronting them might just escalate the issue, though.
MA
Maile
1 year ago
Surprised that the functional manager is being so uncooperative!
JO
Johnna
1 year ago
But what if HR has the staff available? Shouldn't that be checked first?
ST
Stephania
1 year ago
Totally agree, communication is crucial!
BO
Bong
1 year ago
I think talking directly to the functional manager is key.
JO
Jose
1 year ago
I agree with the need for a direct talk, but what if the functional manager is just uncooperative? I wonder if asking leadership for help might be a better option.
LA
Lai
1 year ago
I feel like confronting the functional manager might escalate things. It seems more effective to have a conversation first before evaluating impacts.
MA
Marleen
1 year ago
I'm not sure, but I remember a practice question where involving HR was suggested first. Maybe checking with them could clarify the situation?
YV
Yvonne
1 year ago
I think the best first step is to talk directly to the functional manager. Understanding their reasons could help resolve the issue.
LA
Lang
1 year ago
I think I've got a handle on this. The key is to focus on the specific details in the question and the exhibit, and not make any assumptions.
MA
Ma
1 year ago
Hmm, I'm not too sure about this one. I know WebLogic is an application server, but I'm not very familiar with its specific features. I'll have to think carefully about what sets it apart from a basic Java EE container.
LA
Lai
1 year ago
Okay, I've got this. The four processes are A, B, C, and D. I'm confident those are the right answers.