PMI PMP Exam - Topic 1 Question 50 Discussion
A customer initiated a minor scope change and expects this to be completed without delays or additional costs. The project manager believes that they have adequateauthorization to make the decision themselves but is not quite sure.What should the project manager do next?
C) Use the Perform Integrated Change Control process and submit this to the change control board (CCB) for approval.
A) Use the project contingency and implement the change without charging the customer, since the customer's satisfaction is top priority.
B) Exploit this change opportunity and calculate the cost, risk, and time, then add a reasonable margin and submit to the customer.
D) Keep the change pending and decide to take this up as part of final settlement at the end of the project.
Daren
9 months agoSarah
9 months agoTuyet
9 months agoShawnda
9 months agoMelodie
9 months agoFrank
10 months agoElli
10 months agoLewis
10 months agoNickolas
10 months agoMitsue
10 months agoSilva
10 months agoAlpha
10 months agoShantay
10 months ago