PMI PMP Exam - Topic 1 Question 50 Discussion
A customer initiated a minor scope change and expects this to be completed without delays or additional costs. The project manager believes that they have adequateauthorization to make the decision themselves but is not quite sure.What should the project manager do next?
C) Use the Perform Integrated Change Control process and submit this to the change control board (CCB) for approval.
A) Use the project contingency and implement the change without charging the customer, since the customer's satisfaction is top priority.
B) Exploit this change opportunity and calculate the cost, risk, and time, then add a reasonable margin and submit to the customer.
D) Keep the change pending and decide to take this up as part of final settlement at the end of the project.
Daren
10 months agoSarah
11 months agoTuyet
11 months agoShawnda
11 months agoMelodie
11 months agoFrank
11 months agoElli
11 months agoLewis
11 months agoNickolas
11 months agoMitsue
12 months agoSilva
12 months agoAlpha
12 months agoShantay
12 months ago