PMI PMP Exam - Topic 1 Question 49 Discussion
A project team is executing a megaproject, and several contract requirements have been identified. In the planning phase, the project team agreed that a contract would berequired 3 months prior to the project's finish date. During project execution, it was determined that the contract was required immediately.What should project manager do?
B) Request the team to initiate a change request to execute the contract.
A) Seek management's approval for executing the contract earlier than planned.
C) Support the team's request and allow for early contract execution.
D) Challenge the project team to identify the reasons for early contract execution.
Barrie
10 months agoGerald
11 months agoXuan
11 months agoShelba
11 months agoJeniffer
11 months agoJohnna
11 months agoAnglea
11 months agoLindsey
11 months agoLuther
11 months agoNorah
12 months agoAlline
12 months agoTwana
12 months agoAmber
12 months ago