PMI PMP Exam - Topic 1 Question 49 Discussion
A project team is executing a megaproject, and several contract requirements have been identified. In the planning phase, the project team agreed that a contract would berequired 3 months prior to the project's finish date. During project execution, it was determined that the contract was required immediately.What should project manager do?
B) Request the team to initiate a change request to execute the contract.
A) Seek management's approval for executing the contract earlier than planned.
C) Support the team's request and allow for early contract execution.
D) Challenge the project team to identify the reasons for early contract execution.
Barrie
9 months agoGerald
9 months agoXuan
9 months agoShelba
9 months agoJeniffer
9 months agoJohnna
10 months agoAnglea
10 months agoLindsey
10 months agoLuther
10 months agoNorah
10 months agoAlline
10 months agoTwana
10 months agoAmber
10 months ago