An agile team completes a deliverable that is to be certified by another expert team. The second team does not take the deliverable for many months.What should the servant leader do?
C) Review the process and remove the impediment.
A) Escalate this to the project director for a resolution.
B) Escalate this to the agile lead of the second team.
D) Remove the certification need from the project scope.