PMI PMP Exam - Topic 1 Question 17 Discussion
A key agile project team member takes a leave of absence in the middle of an iteration and will not return to work for a while What should the project manager do next regarding the feature on which the team member was working?
B) Review team capacity and reassign the functionality to additional iterations as required
A) Assign the feature to another team member, and have them try to complete the feature by the end of this iteration
C) Determine if the team member can work from home to complete the functionality.
D) Review the work in progress with the product owner to determine the next step
Jerry
10 months agoCarmelina
11 months agoWalker
11 months agoDexter
11 months agoWilford
11 months agoGlendora
11 months agoMelina
11 months agoFanny
11 months agoJimmie
11 months agoJacki
12 months agoTyra
12 months agoBernadine
12 months agoProvidencia
12 months agoEzekiel
12 months ago