Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMP Topic 1 Question 102 Discussion

Actual exam question for PMI's PMP exam
Question #: 102
Topic #: 1
[All PMP Questions]

A project manager received a request to add features and functions to the project after the scope had already been established. What should the project manager do?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Beckie
4 days ago
I agree with Leota. Following the change management process ensures that any additional features are properly evaluated and integrated into the project.
upvoted 0 times
...
Tom
4 days ago
Haha, the stakeholder engagement process? Really? Might as well throw the project out the window. Change management is the only way to go here.
upvoted 0 times
...
Shannon
6 days ago
I'm going with D. Change management is the way to go. Can't just ignore those new requirements, you know?
upvoted 0 times
...
Leota
16 days ago
I think the project manager should follow the change management process.
upvoted 0 times
...
Nathan
20 days ago
Well, clearly the project manager needs to follow the change management process. Anything else would be a recipe for disaster!
upvoted 0 times
Lewis
5 days ago
B) Follow the stakeholder engagement process.
upvoted 0 times
...
Alayna
5 days ago
B) Follow the stakeholder engagement process.
upvoted 0 times
...
Trinidad
10 days ago
A) Follow the requirements management process.
upvoted 0 times
...
Hana
12 days ago
A) Follow the requirements management process.
upvoted 0 times
...
...
Cornell
21 days ago
What should the project manager do if they receive a request to add features after the scope is set?
upvoted 0 times
...

Save Cancel