You are the project manager for your organization. Management has asked you to document the holidays, weekends, and other corporate working hours, which will supersede the project timings for your schedule. Which calendar will communicate to the project stakeholders, when the project work will take place within the organization?
The float for Activity I is three days. The early start for Activity I is Day 17 and the late start for
Activity I is Day 20. Therefore, the difference of
the early start and the late start reveals the float as three days. It is possible, and acceptable, to use
the difference of the early finish and the late finish to find the float, as the value will be the same
amount. Answer options B, D, and C are incorrect. These are not the valid calculation for the total
float.
Cordelia
10 months agoAlease
10 months agoMireya
10 months agoAnnette
10 months agoAllene
11 months agoFatima
11 months agoIsabelle
11 months agoBrynn
11 months agoAliza
11 months agoScot
11 months agoNorah
11 months agoLettie
11 months agoDonte
11 months agoSharika
11 months agoEliseo
1 year agoYolande
1 year agoKrissy
1 year agoEulah
1 year agoGlory
1 year agoKayleigh
1 year agoElfrieda
1 year agoMattie
1 year agoShawna
1 year agoOna
1 year agoMose
1 year agoBernardo
1 year agoRanee
1 year agoChan
1 year agoSherrell
1 year agoZena
1 year agoDulce
1 year agoRashida
1 year agoBritt
1 year agoKasandra
1 year agoSue
1 year agoAimee
1 year agoFreeman
1 year agoLonny
1 year agoKassandra
1 year agoCecilia
1 year ago